support icon

In April 2020, the following works are being performed at the LUCKY LAND construction site:

  • Building No. 3, Section 1: Work is underway on the installation of vertical elements at the +3,800 m mark and the installation of the floor formwork at the +7,500 m mark.

  • Building No. 3, Section 2: Work is underway on the installation of vertical elements at the +3,800 m mark.

  • Building No. 3, Section 3: The work on the arrangement of the grid was completed and the wall along the deformation seam was reinforced. The parking grid is 100% complete.

House No. 4: 25% opening of the pit has been completed.