In August 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, Section 1:

Construction of the reinforced concrete frame of the 10th floor is in progress;

Bricklaying of the basement, 3rd and 4th floors is underway.

 

Building No. 3, Section 2:

Work is underway to install the floor slab on the 9th floor.

Work is underway to install brickwork from the 5th to the 7th floor.

 

Building No. 3, Section 3:

Work is underway to install the vertical elements of the 6th floor.

 

House No. 4:

Work is underway to reinforce the foundation slab of section 4.3;

Completed works on opening the pit for the parking lot of the 4th phase.

 

Parking:

Completed works on the installation of a reinforced concrete frame.