In August 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
Construction of the reinforced concrete frame of the 10th floor is in progress;
Bricklaying of the basement, 3rd and 4th floors is underway.
Building No. 3, Section 2:
Work is underway to install the floor slab on the 9th floor.
Work is underway to install brickwork from the 5th to the 7th floor.
Building No. 3, Section 3:
Work is underway to install the vertical elements of the 6th floor.
House No. 4:
Work is underway to reinforce the foundation slab of section 4.3;
Completed works on opening the pit for the parking lot of the 4th phase.
Parking:
Completed works on the installation of a reinforced concrete frame.