In December 2020, the following works are being performed at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
Work is underway on the installation of PVC structures from the 3rd to the 10th floor (windows are being installed).
Roof waterproofing is underway.
Work is underway to install risers K1 and K2.
Completed works on the installation of power grid risers.
Works are underway to install waterproofing of the underground part and backfilling.
Building No. 3, Section 2:
Completed works on the installation of power grid risers.
Work is underway to arrange the brickwork of the 13th floor.
Work is underway to install K2 risers.
Work is underway to install waterproofing of the roof.
Backfilling and waterproofing of the underground part is under way.
Building No. 3, Section 3:
Work is underway to arrange the brickwork of the 12th floor.
Completed works on the installation of power grid risers.
Laying on the roof is being done.
Backfilling and waterproofing of the underground part is under way.
Parking
Work is underway to arrange the backfilling of the waterproofing of the underground part and the floor.
Building No. 4, Section 1:
Work is underway to arrange the floor slab of the 5th floor.
Building No. 4, Section 2:
Work is underway to arrange the floor slab of the 3rd floor.
Pit of the sixth turn
The pit of the sixth stage of construction is 90% open.