In July 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
Construction of the reinforced concrete frame of the 8th floor (ceiling above the floor) is underway;
Bricklaying of the basement, 3rd and 4th floors is underway.
Building No. 3, Section 2:
Work is underway to install the vertical elements of the 8th floor.
Bricklaying of the 3rd and 4th floors is underway. Finished basement brickwork.
Building No. 3, Section 3:
Work is underway to install the vertical elements of the 4th floor.
House No. 4:
Concreted foundation slabs of sections 4.1 and 4.2;
Concrete preparation of section 4.3 is completed;
Excavation of the pit for the parking lot of the 4th phase continues.
Parking:
Work is underway to install a part of the floor slab and vertical elements.