support icon

In July 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, Section 1:

Construction of the reinforced concrete frame of the 8th floor (ceiling above the floor) is underway;

Bricklaying of the basement, 3rd and 4th floors is underway.

 

Building No. 3, Section 2:

Work is underway to install the vertical elements of the 8th floor.

Bricklaying of the 3rd and 4th floors is underway. Finished basement brickwork.

 

Building No. 3, Section 3:

Work is underway to install the vertical elements of the 4th floor.

 

House No. 4:

Concreted foundation slabs of sections 4.1 and 4.2;

Concrete preparation of section 4.3 is completed;

Excavation of the pit for the parking lot of the 4th phase continues.

Parking:

Work is underway to install a part of the floor slab and vertical elements.