In March 2020, the following works are being performed at the LUCKY LAND construction site:
Building No. 3, section 1. Installation of formwork and concreting of vertical elements at the -0.700 m mark
Building No. 3, section 2. Reinforcement, installation of formwork and concreting of vertical elements at the -1,600 m mark
Building No. 3, section 3. Work on the arrangement of the grillwork was completed and the wall along the deformation seam was reinforced.
The parking grid (Fm4) is 100% completed.
The parking grid (Fm5) is 100% reinforced.
Completed complex of earthworks for the development of the pit for building No. 4 by 25%.