In October 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
Finished work on the arrangement of the wooden frame.
Work is underway to arrange the brickwork of the 3rd to 9th floors.
Work is underway to arrange the stairwells of the 9th floor.
Installation of ventilation units is completed.
Building No. 3, Section 2:
Finished work on the arrangement of the wooden frame.
Work is underway to arrange the brickwork of the 11th floor.
Work is underway to arrange the staircases on the 11th floor.
Ventilation units have been installed up to the 12th floor.
Building No. 3, Section 3:
Work is underway to arrange the vertical elements of the 13th floor.
Work is underway to arrange the brickwork of the 6th floor.
Work is underway to arrange the staircases on the 11th floor.
Ventilation units have been installed on the 7th floor.
Building No. 4, Section 1:
Work is underway to arrange the vertical elements of the 1st floor.
Building No. 4, Section 2:
Work is underway to arrange the vertical elements of floor -1.