In April 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
⠀
Building No. 3, Section 1:
The installation of PVC constructions of residential floors (on the 12th floor (windows)) has been completed.
Works on the installation of noise insulation in apartments and MOPs have been completed.
Completed works on the installation of engineering communications in apartments and MOS from the 3rd to the 12th floor.
The work on the laying of collateral for electrical wiring in the floors of apartments and commercial buildings from the 3rd to the 12th floor has been completed.
Work is being carried out on the installation of screeds in apartments and MOP from the 3rd to the 5th floor.
Work has begun on the insulation of the facade, loggias and cold passages.
Flooring for the installation of elevators has been installed.
⠀
Building No. 3, Section 2:
The installation of PVC constructions of the residential floors (on the 12th floor (windows)) has been completed.
Work is being carried out on the rolling of noise insulation in front of the engineering communications device in apartments and MOPs.
Work is being carried out on the installation of insulation on the roof superstructure.
⠀
Building No. 3, Section 3:
The installation of PVC constructions of residential floors (on the 13th floor (windows)) has been completed.
Completed works on installation of engineering communications in apartments and MOS from the 2nd to the 13th floor.
The work on the laying of collaterals for electrical wiring in the floors of apartments and commercial buildings from the 2nd to the 13th floor has been completed.
Work was carried out on rolling noise insulation in apartments and commercial buildings.
⠀
Parking:
The works on the installation of waterproofing and the opening of the ceiling have been completed.
⠀
Building No. 4, Section 1:
Work is underway to arrange the vertical elements of the 13th floor.
Completed brickwork on the 3rd, 4th, 5th, 6th floors. Work is underway on -1, 7, 8, 9, 10 floors.
Completed works on the arrangement of the stylobate part of floors -2 and -1.
Work is being carried out on the installation of vertical waterproofing of the underground part.
⠀
Building No. 4, Section 2:
The floor of the 10th floor is concreted.
Finished brickwork on the 3rd, 4th, 5th floor. Work is underway on the 6th, 7th, 8th, and 9th floors.
Completed works on the arrangement of the stylobate part of floors -2 and -1.
Work is being carried out on the installation of vertical waterproofing of the underground part.
⠀
Building No. 4, Section 3:
Work is underway to arrange the floor slab of the 2nd floor.
Completed works on the arrangement of the stylobate part of floors -2 and -1.
Work is being carried out on the installation of vertical waterproofing of the underground part.
⠀
Building No. 6, Section 2:
Work is being carried out on the arrangement of the ceiling above the first floor.
Work is being carried out on the installation of vertical waterproofing of the underground part.
⠀
Building No. 6, Section 1:
Work is underway to install the vertical elements of the 2nd floor.
Work is being carried out on the installation of vertical waterproofing of the underground part.
⠀
Building No. 6, parking lot:
The Fm3 foundation slab is concreted.
Work is underway to install vertical elements.
Work is being carried out on the installation of vertical waterproofing of the underground part.