In July 2021, the following works will be carried out at the construction site of the "LUCKY LAND" housing complex:
⠀
Building No. 3, Section 1:
The screed installation work on the MZK 13th floor has been completed.
Works on insulation and facade decoration are being carried out.
Installation of elevator equipment is being carried out.
Installation of apartment switchboards is being carried out.
Work is being carried out on the installation of fasteners under the stained glass windows of the first floors.
Installation of PVC structures on cold passages and vestibules has been completed.
Work is underway to install metal fences on stairwells and cold passages.
Installation of fire alarm cabling in apartments and office premises has been completed.
⠀
Building No. 3, Section 2:
The screeding work on the apartments and MZK from the 9th to the 13th floor has been completed.
Works on insulation and facade decoration are being carried out.
Installation of elevator equipment is being carried out.
Installation of PVC structures on cold passages and vestibules has been completed.
Work is underway to install metal fences on stairwells and cold passages.
Installation of fire alarm cabling in apartments and office premises has been completed.
⠀
Building No. 3, Section 3:
The screeding work on the apartments and MZK from the 3rd to the 11th floor has been completed.
Works on insulation and facade decoration are being carried out.
Installation of elevator equipment is being carried out.
Installation of fire alarm cabling in apartments and office premises has been completed.
Work is underway to install metal fences on stairwells and cold passages.
Building No. 3, Parking:
Works on the arrangement of the splinker fire extinguishing system are being carried out.
Work is being carried out on the installation of fire alarm cabling.
Building No. 4, Section 1:
Brickwork on the roof is completed.
Roof waterproofing is being carried out.
⠀
Building No. 4, Section 2:
The ceiling of the 13th floor is concreted.
Brickwork is being done on the 12th floor.
Work is being carried out on the installation of vertical elements of the stylobate part of the 2nd floor.
Building No. 4, Section 3:
Work is underway to install the vertical elements of the 11th floor.
Work on the installation of vertical elements of the stylobate part of the 1st floor is being carried out.
Work is underway to install brickwork from the 3rd to the 7th floor.
⠀
Building No. 6, Section 1:
Work on the installation of the floor slab of the 3rd floor is being carried out.
Building No. 6, Section 2:
Work on the arrangement of the vertical elements of the 4th floor is being carried out.
Building No. 5, Section 1, 2, 3:
Work on opening the pit is in progress.