In June 2021, the following works will be performed at the construction site of the "LUCKY LAND" housing complex:

Building No. 3, Section 1:

Work has been completed on the arrangement of the screed in the apartments and the MOP from the 3rd to the 12th floor.

Works on insulation of the facade are being carried out.

Works on installation of elevator equipment are being carried out.

The screeds of floors -2 and -1 have been installed.

Work has begun on the installation of fasteners under the stained glass windows of the first floors.

Installation of cable distribution, water supply and heating in apartments has been completed.

Building No. 3, Section 2:

Work has been completed on the arrangement of the screed in the apartments and the MOP from the 3rd to the 8th floor.

Works on insulation of the facade are being carried out.

Works on installation of elevator equipment are being carried out.

The work on the arrangement of the floor screed -1 has been completed.

Work has begun on the installation of fasteners under the stained glass windows of the first floors.

Installation of cable distribution, water supply and heating in apartments has been completed.

Building No. 3, Section 3:

Work has been completed on the arrangement of the screed in the apartments and the MOP from the 3rd to the 7th floor.

Works on insulation of the facade are being carried out.

Works on installation of elevator equipment are being carried out.

The work on the arrangement of the floor screed -1 has been completed.

Work has begun on the installation of fasteners under the stained glass windows of the first floors.

Installation of cable distribution, water supply and heating in apartments has been completed.

Building No. 4, Section 1:

Completed works on the installation of a monolithic frame.

Brickwork is completed from the 3rd to the 13th floor. Work is underway on the roof.

Building No. 4, Section 2:

The floor of the 11th floor is concreted.

Brickwork is completed from the 3rd to the 10th floor. Work is underway on the 11th floor.

Work is being carried out on the arrangement of the floor slab of the stylobate part of the 1st floor.

 

Building No. 4, Section 3:

Work is underway to arrange the vertical elements of the 9th floor.

Work on the installation of vertical elements of the stylobate part of the 1st floor is being carried out.

Work has begun on the installation of brickwork on the 3rd and 4th floors.

Building No. 6, Section 2:

Work on the arrangement of the vertical elements of the 3rd floor is being carried out.

Building No. 6, Section 1:

Work on the arrangement of the vertical elements of the 3rd floor is being carried out.

Building No. 5, section 5.3 and 5.2

Pit opening works are being carried out