In March 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, Section 1:

Installed PVC structures from the 3rd to the 12th floor (windows).

Work on the installation of engineering communications in apartments and MZK from the 3rd to the 8th floor has been completed.

Completed work on the installation of electrical wiring in the floors of apartments and MZK from the 3rd to the 7th floor.

PVC constructions of loggias from the 3rd to the 12th floor (windows) are being installed.

Building No. 3, Section 2:

Completed works on the installation of power grid risers.

Finished work on the arrangement of brickwork.

Completed work on the arrangement of risers K1 and K2.

Building No. 3, Section 3:

PVC constructions are installed from the 8th to the 13th floor (windows).

Work is being carried out on the installation of engineering communications in apartments and MZK from the 2nd to the 4th floor.

Work is being carried out on the installation of electrical wiring in the floors of apartments and MZK from the 2nd to the 4th floor.

Parking

Work is underway to install waterproofing of the floor.

Building No. 4, Section 1:

Work is underway to arrange the floor slab of the 10th floor.

Brickwork is being done on the 3rd and 4th floors.

Building No. 4, Section 2:

Work is underway to arrange the floor slab of the 9th floor.

Brickwork is being done on the 3rd and 4th floors.

Building No. 4, Section 3:

Work is underway to arrange the vertical elements of the 1st floor.

Building 6, section 2

Work on the arrangement of vertical elements of the -1st floor is being carried out.

Building 6, section 1

Work is underway on the installation of the floor slab - 1st floor.