support icon

The progress of construction in the Lucky Land residential complex in September 2021

A comfort-class residential complex located next to 100 hectares of ancient forest. This is a real city within a city with developed infrastructure, kindergartens and a school.

Building No. 3, Section 1:

• Plastering of technical premises is being carried out.

• Glazing of the first floors is underway.

• Work is underway to install metal fences on stairwells and cold passages.

• Installation of splinker fire extinguishing systems in basements is underway.

• Works on the ventilation and smoke removal system are being carried out.

Building No. 3, Section 2:

• Works on insulation and decoration of the facade are being carried out.

• Plastering of technical premises is being carried out.

• Glazing of the first floors is underway.

• Work is underway to install metal fences on stairwells and cold passages.

• Installation of splinker fire extinguishing systems in basements is underway.

• Works on the ventilation and smoke removal system are being carried out.

Building No. 3, Section 3:

• Works on insulation and decoration of the facade are being carried out.

• Plastering of technical premises is being carried out.

• Glazing of the first floors is underway.

• Work is underway to install metal fences on stairwells and cold passages.

• Installation of splinker fire extinguishing systems in basements is underway.

• Works on the ventilation and smoke removal system are being carried out.

Building No. 3, parking lot:

• Works on the installation of the splinker fire extinguishing system are being carried out.

• Fire alarm cabling installation works are being carried out.

• Works on installation of smoke removal and ventilation systems are being carried out.

• Works on the installation of storm sewers are being carried out.

• Works on the arrangement of fire-fighting water supply are being carried out.

• Works on laying and arrangement of electricity supply are being carried out.

Building No. 4, Section 1:

• Installation of PVC structures from the 3rd to the 13th floor is underway.

Building No. 4, Section 2:

• Installation of PVC structures from the 3rd to the 13th floor is underway.

• Roofing works are underway.

Building No. 4, Section 3:

• Work is underway to arrange the brickwork from the 11th to the 12th floor.

Building No. 6, Section 1:

• Work on the arrangement of the vertical elements of the 7th floor is being carried out.

Building No. 6, Section 2:

• Work on the installation of the floor slab of the 7th floor is being carried out.

Building No. 5, Section 1, 2, 3:

• Work on the arrangement of the vertical elements of the underground part of sections 1 and 2 is being carried out.

• The foundation plate of the tower crane is made.