In February 2021, the following works are being performed at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
Work is underway on the construction of PVC structures on the 11th - 12th floors (windows are being installed).
Completed works on waterproofing the roof.
Completed work on the arrangement of risers K1 and K2.
Work has begun on the installation of engineering communications in apartments and MZK.
Completed works on the installation of power grid risers.
Completed works on waterproofing the underground part and backfilling.
Building No. 3, Section 2:
Completed works on the installation of power grid risers.
Finished work on the arrangement of brickwork.
Completed work on the arrangement of risers K1 and K2.
Completed works on waterproofing the roof.
Completed works on waterproofing the underground part and backfilling.
Building No. 3, Section 3:
Work is underway to arrange the brickwork of the 13th floor.
Completed works on the installation of power grid risers.
Completed work on the arrangement of risers K1 and K2.
Completed works on waterproofing the roof.
Completed works on waterproofing the underground part and backfilling.
Parking
Work is underway to install waterproofing of the floor.
Building No. 4, Section 1:
Work is underway to arrange the floor slab of the 8th floor.
Brickwork is being done on the 3rd floor.
Building No. 4, Section 2:
Work is underway to arrange the floor slab of the 7th floor.
Building No. 4, Section 3:
Work is underway on the installation of the floor slab - 2nd floor.
Parking
Grills Fm-5, Fm-6 and Fm-8 were made.
Building 6, section 6.3 and 6.2
The Fm-2 foundation slab was made.
Work has begun on the arrangement of vertical elements -1 floor
Building 6, section 6.1
Reinforcement of the Fm-1 foundation slab is being carried out.