In January 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, Section 1:

Work is underway on the installation of PVC structures from the 3rd to the 10th floor (windows are being installed).

Completed works on waterproofing the roof.

Completed works on arrangement of risers K1 and K2.

Completed works on the installation of power grid risers.

Works are underway to install waterproofing of the underground part and backfilling.

Building No. 3, Section 2:

Completed works on the installation of power grid risers.

Finished work on the arrangement of brickwork.

Completed works on arrangement of risers K1 and K2.

Completed works on waterproofing the roof.

Backfilling and waterproofing of the underground part are being carried out.

Building No. 3, Section 3:

Work is underway to arrange the brickwork of the 13th floor.

Completed works on the installation of power grid risers.

Work is underway to install risers K1 and K2.

Roof waterproofing is in progress.

Backfilling and waterproofing of the underground part is under way.

Parking

Work is underway to arrange the backfilling of the waterproofing of the underground part and the floor.

Building No. 4, Section 1:

Work is underway to arrange the vertical elements of the 6th floor.

Building No. 4, Section 2:

Work is underway to arrange the floor slab of the 5th floor