In November, the following works were performed at the construction site of OLEGIVSKYI BFK
Section 1: Pit development - 100%;
Arrangement of pile field - 50%.
Section 2:
Installation of sheet pile fencing - 100%; Pit development - 100%.
Section 3:
Installation of sheet pile fencing - 100%; Pit development - 100%.
Section 4:
Installation of sheet pile fencing - 100%;
Pit development - 100%.
Section 5:
Pit development - 100%;
Arrangement of pile field - 50%.
Parking:
Pit development - 95%.