Construction progress for February 2022

28.02.2022

Go back

Construction progress at BFC Olegivskiy for February 2022

The Olegivskiy business-class residential complex is located in the heart of the historical center of Kyiv on Podil. The house is designed in a restrained modern style and is located on the highest point of Shchekavitsa mountain. The project includes a lounge area in the yard and on the roof, an outdoor fireplace, a fitness area, a children's area and much more.

In February, the following works were performed at the construction site of BFC Olegivskiy:

Section 1:

Arrangement of foundations - 100%;

Installation of backfilling - 100%;

Arrangement of the power plate - 60%.

Section 2:

Arrangement of foundations - 100%;

Installation of backfilling - 100%;

Arrangement of the power plate - 20%.

Section 3:

Arrangement of foundations - 50%;

Arrangement of backfilling - 50%.

Section 4:

Arrangement of foundations - 47%;

Installation of backfill - 50%.

Section 5:

Arrangement of pile field - 100%;

Arrangement of foundations - 55%;

Installation of backfilling - 40%.

Parking:

Arrangement of pile field - 100%;

Arrangement of foundations - 13%;

Arrangement of backfilling - 8%.