Construction progress for February 2022
28.02.2022
Construction progress at BFC Olegivskiy for February 2022
The Olegivskiy business-class residential complex is located in the heart of the historical center of Kyiv on Podil. The house is designed in a restrained modern style and is located on the highest point of Shchekavitsa mountain. The project includes a lounge area in the yard and on the roof, an outdoor fireplace, a fitness area, a children's area and much more.
In February, the following works were performed at the construction site of BFC Olegivskiy:
Section 1:
Arrangement of foundations - 100%;
Installation of backfilling - 100%;
Arrangement of the power plate - 60%.
Section 2:
Arrangement of foundations - 100%;
Installation of backfilling - 100%;
Arrangement of the power plate - 20%.
Section 3:
Arrangement of foundations - 50%;
Arrangement of backfilling - 50%.
Section 4:
Arrangement of foundations - 47%;
Installation of backfill - 50%.
Section 5:
Arrangement of pile field - 100%;
Arrangement of foundations - 55%;
Installation of backfilling - 40%.
Parking:
Arrangement of pile field - 100%;
Arrangement of foundations - 13%;
Arrangement of backfilling - 8%.