Construction progress for October 2024
06.11.2024
Go back
We share the latest news from the construction site for October:
Building No. 3, parking:
- installation of polymer coating of parking floors.
Building No. 3, landscaping:
- external lighting installation continues;
- tree planting continues;
- landscaping of the courtyard;
- installation of access control systems, including barriers, video surveillance.
Building No. 4:
- installation of external power supply networks;
- installation of smoke removal and ventilation systems of the parking lot;
- installation of waterproofing of the parking lot;
- installation of finishing of technical premises (floor screed, plaster);
- installation of the roof of the parking lot of the external and internal courtyard.
Building No. 4, section 1:
- installation of finishing of the MZK from the 4th to the 7th floor;
- decoration of the facades of the LMM continues;
- installation of monolithic structures of stylobates under the SPOK;
- installation of waterproofing of monolithic structures under the SPOK;
- installation of translucent enclosing structures (SPOK);
- work continues on arranging the masonry of the 1st and 2nd floors;
- installation of PVC structures on cold passages, vestibules of the MZK;
- installation of smoke exhaust and ventilation systems;
- installation of plastering of technical rooms.
Building No. 4, section 2:
- decoration of the facades of the LMM continues;
- installation of ceramic tiles in the MZK on the 4th and 5th floors;
- installation of monolithic structures of stylobates under the SPOK;
- installation of waterproofing of monolithic structures under the SPOK;
- installation of masonry of the 1st and 2nd floors;
- installation of smoke exhaust and ventilation systems;
- installation of translucent enclosing structures (SPOK);
- installation of PVC structures on cold passages, vestibules of the MZK.
Building No. 4, section 3:
- installation of screeds 9-13 floors;
- installation of monolithic structures of stylobates under the SPOK;
- installation of smoke exhaust and ventilation systems;
- installation of lightning protection systems;
- installation of PVC structures on cold passages, vestibules of the MZK.
Building No. 5, section 1:
- works on the installation of walls and partitions on the 10th floor continue.
Building No. 5, section 2:
- installation of vertical and horizontal elements of the monolithic frame on the 14th floor, machine room, parapets on the roof;
- installation of walls and partitions on the 10th floor;
- installation of ventilation units on the 13th-14th floor.
Building No. 5, section 3:
- installation of vertical and horizontal elements of the monolithic frame on the 12th floor.
- installation of ventilation units from the 6th-9th floors.
Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):
- installation of vertical elements of the monolithic frame on the 1st floor.
Building No. 5, parking lot 1.5 (parking lot adjacent to sections 1-2):
- installation of vertical and horizontal elements of the monolithic frame - 1st turn.
Building No. 6, section 1:
- installation of walls and partitions in the basement;
- installation of gates and doors in TP4;
- manufacture of PVC structures 4-7 floors.
Building No. 6, section 2:
- installation of walls and partitions in the basement.