Lucky Land
Construction progress for October 2024

06.11.2024

Go back

We share the latest news from the construction site for October:

Building No. 3, parking:

  • installation of polymer coating of parking floors.

Building No. 3, landscaping:

  • external lighting installation continues;
  • tree planting continues;
  • landscaping of the courtyard;
  • installation of access control systems, including barriers, video surveillance.

Building No. 4:

  • installation of external power supply networks;
  • installation of smoke removal and ventilation systems of the parking lot;
  • installation of waterproofing of the parking lot;
  • installation of finishing of technical premises (floor screed, plaster);
  • installation of the roof of the parking lot of the external and internal courtyard.

Building No. 4, section 1:

  • installation of finishing of the MZK from the 4th to the 7th floor;
  • decoration of the facades of the LMM continues;
  • installation of monolithic structures of stylobates under the SPOK;
  • installation of waterproofing of monolithic structures under the SPOK;
  • installation of translucent enclosing structures (SPOK);
  • work continues on arranging the masonry of the 1st and 2nd floors;
  • installation of PVC structures on cold passages, vestibules of the MZK;
  • installation of smoke exhaust and ventilation systems;
  • installation of plastering of technical rooms.

Building No. 4, section 2:

  • decoration of the facades of the LMM continues;
  • installation of ceramic tiles in the MZK on the 4th and 5th floors;
  • installation of monolithic structures of stylobates under the SPOK;
  • installation of waterproofing of monolithic structures under the SPOK;
  • installation of masonry of the 1st and 2nd floors;
  • installation of smoke exhaust and ventilation systems;
  • installation of translucent enclosing structures (SPOK);
  • installation of PVC structures on cold passages, vestibules of the MZK.

Building No. 4, section 3:

  • installation of screeds 9-13 floors;
  • installation of monolithic structures of stylobates under the SPOK;
  • installation of smoke exhaust and ventilation systems;
  • installation of lightning protection systems;
  • installation of PVC structures on cold passages, vestibules of the MZK.

Building No. 5, section 1:

  • works on the installation of walls and partitions on the 10th floor continue.

Building No. 5, section 2:

  • installation of vertical and horizontal elements of the monolithic frame on the 14th floor, machine room, parapets on the roof;
  • installation of walls and partitions on the 10th floor;
  • installation of ventilation units on the 13th-14th floor.

Building No. 5, section 3:

  • installation of vertical and horizontal elements of the monolithic frame on the 12th floor.
  • installation of ventilation units from the 6th-9th floors.

Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):

  • installation of vertical elements of the monolithic frame on the 1st floor.

Building No. 5, parking lot 1.5 (parking lot adjacent to sections 1-2):

  • installation of vertical and horizontal elements of the monolithic frame - 1st turn.

Building No. 6, section 1:

  • installation of walls and partitions in the basement;
  • installation of gates and doors in TP4;
  • manufacture of PVC structures 4-7 floors.

Building No. 6, section 2:

  • installation of walls and partitions in the basement.