Construction progress for December 2024

30.12.2024

Go back

We share the latest news from the construction site for December:

House No. 3, landscaping:

  • landscaping of the courtyard.

House No. 4:

  • installation of external power supply networks;
  • installation of smoke extraction and parking ventilation systems.

Building No. 4, section 1:

  • Internal finishing works of the MZK are being carried out;
  • facade decoration;
  • masonry work continues;
  • installation of smoke extraction and ventilation systems;
  • installation of plaster and ceramic tiles in technical rooms;
  • installation of water supply systems;
  • installation of a storm sewer system.

Building No. 4, section 2:

  • facade decoration;
  • installation of monolithic stylobate structures under the SPOK;
  • installation of waterproofing of monolithic structures under SPOK;
  • masonry arrangement;
  • installation of smoke extraction and ventilation systems;
  • The installation of translucent enclosing structures (SPOK) continues.

Building No. 4, section 3:

  • installation of apartment power supply networks 12, 13 floors;
  • installation of smoke extraction and ventilation systems;
  • installation of ceramic tiles in the MZK on floors 8-13;
  • finishing works of the MZK continue;
  • plastering in technical rooms.

Building No. 5, section 1:

  • work continues on installing walls and partitions on floors 6 and 10;
  • installation of staircases and landings on the 11th and 12th floors.

Building No. 5, section 2:

  • installation of vertical and horizontal elements of the monolithic frame of the 14th floor, technical rooms and parapets;
  • installation of VB 13, 14 floors;
  • installation of walls and partitions 6, 10 floors.

Building No. 5, section 3:

  • installation of vertical elements of the monolithic frame on the 12th floor;
  • installation of ventilation units on floors 6 and 7 continues;
  • installation of walls and partitions on the 4th and 5th floors.

Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):

  • installation of vertical waterproofing.

Building No. 5, 1.5 (parking lot adjacent to sections 1-2):

  • installation of vertical elements of the monolithic frame of the 1st floor.

Building No. 6, section 1:

  • Work continues on glazing windows and installing PVC structures;
  • the construction of walls and partitions in the basement continues;
  • installation of elevator equipment.

Building No. 6, section 2:

  • the construction of walls and partitions in the basement continues;
  • installation of elevator equipment.