Construction progress for December 2024
30.12.2024
Go back
We share the latest news from the construction site for December:
House No. 3, landscaping:
- landscaping of the courtyard.
House No. 4:
- installation of external power supply networks;
- installation of smoke extraction and parking ventilation systems.
Building No. 4, section 1:
- Internal finishing works of the MZK are being carried out;
- facade decoration;
- masonry work continues;
- installation of smoke extraction and ventilation systems;
- installation of plaster and ceramic tiles in technical rooms;
- installation of water supply systems;
- installation of a storm sewer system.
Building No. 4, section 2:
- facade decoration;
- installation of monolithic stylobate structures under the SPOK;
- installation of waterproofing of monolithic structures under SPOK;
- masonry arrangement;
- installation of smoke extraction and ventilation systems;
- The installation of translucent enclosing structures (SPOK) continues.
Building No. 4, section 3:
- installation of apartment power supply networks 12, 13 floors;
- installation of smoke extraction and ventilation systems;
- installation of ceramic tiles in the MZK on floors 8-13;
- finishing works of the MZK continue;
- plastering in technical rooms.
Building No. 5, section 1:
- work continues on installing walls and partitions on floors 6 and 10;
- installation of staircases and landings on the 11th and 12th floors.
Building No. 5, section 2:
- installation of vertical and horizontal elements of the monolithic frame of the 14th floor, technical rooms and parapets;
- installation of VB 13, 14 floors;
- installation of walls and partitions 6, 10 floors.
Building No. 5, section 3:
- installation of vertical elements of the monolithic frame on the 12th floor;
- installation of ventilation units on floors 6 and 7 continues;
- installation of walls and partitions on the 4th and 5th floors.
Building No. 5, parking lot 1.6 (parking lot adjacent to section 3):
- installation of vertical waterproofing.
Building No. 5, 1.5 (parking lot adjacent to sections 1-2):
- installation of vertical elements of the monolithic frame of the 1st floor.
Building No. 6, section 1:
- Work continues on glazing windows and installing PVC structures;
- the construction of walls and partitions in the basement continues;
- installation of elevator equipment.
Building No. 6, section 2:
- the construction of walls and partitions in the basement continues;
- installation of elevator equipment.