Construction progress for October 2022

20.10.2022

Go back

Ambitious and ultra-modern Metropolis by DIM is the decoration of the Holosiiv district, welcoming its guests with the grandeur of architecture and technological solutions.

It grows every day, as does our faith in the soon Victory. We thank our tireless builders and investors who conscientiously pay the installments.

We share the construction report for October, we are on schedule!

Building No. 3, Section 1:

  • arrangement of internal brick walls from the 3rd to the 34th floor - 96%;

  • completed works on laying heating pipelines for apartments - 93%;

  • installation of fire valves per apartment - 96%;

  • installation of a cement-sand screed floor - 55%;

  • laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 82%;

  • placement of NVF - 55%;

  • arrangement of SPOK - 17%;

  • arrangement of the roof - 70%.

Building No. 3, Section 2:

  • arrangement of internal brick walls from the 3rd to the 11th floor - 93%;

  • laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 97%;

  • placement of NVF - 82%;

  • arrangement of SPOK - 92%;

  • arrangement of the roof - 53%;

  • arrangement of LMM of the building - 43%.

Building No. 3, Section 3:

  • arrangement of internal brick walls from the 3rd to the 34th floor - 99%;

  • installation of fire valves per apartment - 99%;

  • installation of a cement-sand screed floor - 90%;

  • placement of NVF - 92%;

  • arrangement of SPOK - 93%;

  • arrangement of LMM - 45%;

  • laying tiles on the floor in MZK - 37%.

Railway station parking lot No. 3:

arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 - 70%.