Construction progress for September 2022
01.10.2022
Construction progress at Metropolis in September 2022
At the beginning of autumn, the construction of the cozy Comfort+ class complex "Metropolis", located next to the VDNG Park and the Holosiivsky Forest, made significant progress.
In September 2022, the following works were performed at the Metropolis construction site:
Building No. 3, Section 1:
arrangement of internal brick walls from the 3rd to the 34th floor - 95%;
completed works on laying heating pipelines for apartments - 92%;
installation of fire valves by apartment - 95%;
digitization of the openings of the passage of engineering communications in apartments and MZK - 100%;
laying of electrical networks (horizontal) for powering apartments and boilers, MZK - 80%;
placement of NVF - 50%;
arrangement of SPOK - 15%;
arrangement of the roof - 40%;
decoration of the walls of the elevator shaft - 100%.
Building No. 3, Section 2:
arrangement of internal brick walls from the 3rd to the 11th floor - 90%;
completed works on laying heating pipelines for apartments - 100%;
installation of a cement-sand screed floor - 100%;
digitization of the openings of the passage of engineering communications in apartments and MZK - 100%;
laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 97%;
placement of NVF - 80%;
arrangement of SPOK - 90%;
arrangement of LMM of the building - 40%;
Building No. 3, Section 3:
arrangement of internal brick walls from the 3rd to the 34th floor - 99%;
installation of fire valves per apartment - 99%;
installation of a cement-sand screed floor - 80%;
digitization of the openings of the passage of engineering communications in apartments and MZK - 99%;
laying of electrical networks (horizontal) for supplying apartments and boilers, MZK - 99%;
placement of NVF - 90%;
arrangement of SPOK - 95%;
decoration of the walls of the elevator shaft - 100%;
laying tiles on the floor in MZK - 30%.
Railway station parking lot No. 3:
Arrangement of s/b structures:
Pylons - 100%;
Floor slab - 100%;
Cover plate - 90%;
Arrangement of cement-sand screed of technical premises - 100%.
Building No. 4, Section 1:
Arrangement of s/b structures:
Floor slab 11-12 floor;
Reinforcement of floor slabs on the 13th floor;
Railway station parking lot No. 3, 3rd starting point:
1. Pylons - 50%;
2. Floor slab - 95%
3. Cover plate - 50%.
4. Installation of grills - 15%