Construction progress for July 2022

20.07.2022

Go back

The residential complex "Novyi Avtograf"is located next to the "Peremoha" park, 15 minutes from the "Darnytsia"metro station. The residential complex is designed to consist of two buildings, united by a closed territory with constant video surveillance, underground parking, children's and sports grounds. The main thing is that the complex implements the concept of "yard without cars"

In July, the following work was completed at the construction site of the residential complex:

Building No. 1, section 1:

  • Installation of decorative plaster on the cold staircase – 100%.

  • Installation of floor tiles on the 26th floor – 100%

  • Installation of decorative plaster 26th floor -100%

  • Preparation of floors for painting from the 2nd to the 26th -95%

  • Installing tiles on a warm staircase -70%

  • Installation of radiators from the 2nd to the 26th floor – 100%.

  • Installation of water supply units in floor niches OV -80%

  • Installation of floor technical hatches – 85%

  • Installation of aluminum structures (doors) on staircases – 100%

  • Installation of terrace parapet covers on the 7th floor - 100%

Building No. 1, section 2:

  • Installing tiles on the staircase -100%

  • Installation of water supply units in floor niches OV -80%

  • Installation of floor technical hatches – 85%

  • Installation of terrace parapet covers on the 5th floor - 90%

  • Installation of parapet covers on the roof - 100%

  • Installation of drains on balconies and HP -100%

  • Installation of fencing on balconies and terraces -100%

Building No. 1, section 3:

  • Installing tiles on a cold staircase – 100%

  • Installing tiles on a warm staircase -90%

  • Preparation of MZK for painting – 70%

  • Installation of radiators from the 2nd to the 22nd floor – 100%.

  • Installation of water supply units in floor niches OV -80%

  • Installation of floor technical hatches – 85%

  • Installation of terrace parapet covers on the 5th floor - 90%

  • Installation of parapet covers on the roof -70%

House No. 2:

  • Installation of floor tiles on the 25th floor – 90%

  • Installation of puttying ceilings from the 19th to the 25th -100%

  • Wall puttying from the 19th to the 25th - 40%

  • Warm staircase installation, puttying of walls and ceilings -100%

  • Cold staircase installation of decorative plaster - 95%

  • Installation of floor technical hatches – 40%

  • Installation of radiators from the 3rd to the 26th floor – 100%

  • Installation of LMM (wet facade) - 90%

  • SPOK device -100%

  • Installation of aluminum structures 1st, 2nd floor – 90%

Parking:

  • Monolithic works – 80%.

External networks:

  • Installation of the casing for K1 (drilling of the well) – 80 linear meters