Construction progress for February 2024

26.02.2024

Go back

The Novyi Autograph by DIM is completing construction!

We share a fresh report from the construction site for February:

Building No. 1, Section 1:

  • installation of insulation on water supply and sewage pipelines in the basement - 60%;
  • arrangement of a wall corner on the ceiling in the MZK - 60%;
  • installation of video surveillance cameras in the forehead - 100%;
  • installation of facade lamps - 90%.

Building No. 1, Section 2:

  • arrangement of the MZK cubic rail - 40%;
  • arrangement of a wall corner on the ceiling in the MZK - 95%;
  • installation of video surveillance cameras in the forehead - 100%;
  • installation of facade lamps - 90%.

Building No. 1, Section 3:

  • arrangement of a wall corner on the ceiling in the MZK - 30%;
  • installation of video surveillance cameras in the forehead - 100%;
  • installation of facade lamps - 70%.

House No. 2:

  • puttying exits from the basement (commercial premises) - 100%;
  • arrangement of tiles on the floor of the elevator hall dept. -1 (transition from the parking lot to railway station No. 2) – 100%;
  • installation of terrace heating - 100%;
  • installation of cable products on fans on the roof of non-residential premises - 100%;
  • installation of MZK heating cable products (connection of convectors) - 100%;
  • installation of air conditioner baskets - 100%;
  • installation of the terrace fence - 100%;
  • installation of facade lamps - 60%.

Parking:

  • arrangement of the parking lot roof - 50%;
  • arrangement of protective concrete of the roof - 50% (2200 m2);
  • installation of automation of fire protection systems - 100%;
  • installation of an electric panel parking lot - 90%;
  • arrangement of connecting electric car chargers - 100%.

External networks:

  • installation of supports, external lighting fixtures around the residential complex - 100% (on Knyaz Romana Mstislavich Street).

Landscaping:

  • TP1, TP2, installation of KL 0.4 kV, installation of KL 10 kV;
  • arrangement of sound insulation TP2 - 90%;
  • assembly of busbars RU-10 kV, RU-0.4 kV in TP1 - 100%;
  • assembly of busbars RU-10 kV, RU-0.4 kV in TP2 - 100%;
  • installation of RU-10 kV TP1 – 90%;
  • installation of RU-10 kV TP2 - 90%;
  • installation of RU-0.4 kV TP1 - 50%;
  • installation of RU-0.4 kV TP2 - 50%;
  • arrangement of grounding TP1, TP2 - 70%.