Construction progress for January 2024
23.01.2024
Go back
The new Autograph by DIM is completing construction!
We share a fresh report from the construction site for January:
Building No. 1, Section 1:
- arrangement of electric heating of basement pipes - 100%;
- installation of the MZK cubic rail - 80%;
- stairwell fence installation - 100%.
Building No. 1, Section 2:
- installation of the MZK cubic rail - 20%;
- arrangement of electric heating of basement pipes - 100%;
- stairwell fence installation - 100%.
Building No. 1, Section 3:
- stairwell fence installation - 100%.
House No. 2:
- installation of air conditioner baskets - 85%;
- installation of power supply of the smoke removal system of non-residential premises - 100%;
- installation of stairwell fencing - 100%;
- installation of the terrace fence - 20%;
- installation of electrical systems and automation of the boiler room and ITP - 100%.
Parking:
- installation of insulation on water supply pipelines (railway No. 1 C1,3 transit through the parking lot) - 85%;
- arrangement of the parking lot roof - 45%;
- installation of an electric panel parking lot - 80%.
External networks:
- installation of floor coverings for electric cables and arrangement of foundations for outdoor lighting around the residential complex - 100% (on Knyaz Romana Mstislavych St. it was done in December).
Landscaping:
- TP1, TP2, installation of KL 0.4 kV, installation of KL 10 kV;
- arrangement of sound insulation TP2 - 80%;
- installation of gates and gratings TP1, TP2 - 80%;
- arrangement of grounding TP1, TP2 - 50%;
- installation of a tray system under 0.4 kV C3 basement - 70%;
- arrangement of shelves for 0.4 kV HV #2 - 50%;
- arrangement of shelves for 0.4 kV TP1 cable floor - 80%;
- arrangement of tray system and shelves under 0.4 kV in switchboard C3 - 100%.