Novyi Autograph
Construction progress for January 2024

23.01.2024

Go back

The new Autograph by DIM is completing construction!

We share a fresh report from the construction site for January:

Building No. 1, Section 1:

  • arrangement of electric heating of basement pipes - 100%;
  • installation of the MZK cubic rail - 80%;
  • stairwell fence installation - 100%.

Building No. 1, Section 2:

  • installation of the MZK cubic rail - 20%;
  • arrangement of electric heating of basement pipes - 100%;
  • stairwell fence installation - 100%.

Building No. 1, Section 3:

  • stairwell fence installation - 100%.

House No. 2:

  • installation of air conditioner baskets - 85%;
  • installation of power supply of the smoke removal system of non-residential premises - 100%;
  • installation of stairwell fencing - 100%;
  • installation of the terrace fence - 20%;
  • installation of electrical systems and automation of the boiler room and ITP - 100%.

Parking:

  • installation of insulation on water supply pipelines (railway No. 1 C1,3 transit through the parking lot) - 85%;
  • arrangement of the parking lot roof - 45%;
  • installation of an electric panel parking lot - 80%.

External networks:

  • installation of floor coverings for electric cables and arrangement of foundations for outdoor lighting around the residential complex - 100% (on Knyaz Romana Mstislavych St. it was done in December).

Landscaping:

  • TP1, TP2, installation of KL 0.4 kV, installation of KL 10 kV;
  • arrangement of sound insulation TP2 - 80%;
  • installation of gates and gratings TP1, TP2 - 80%;
  • arrangement of grounding TP1, TP2 - 50%;
  • installation of a tray system under 0.4 kV C3 basement - 70%;
  • arrangement of shelves for 0.4 kV HV #2 - 50%;
  • arrangement of shelves for 0.4 kV TP1 cable floor - 80%;
  • arrangement of tray system and shelves under 0.4 kV in switchboard C3 - 100%.