Construction progress for November 2023
21.11.2023
OLEGIV Podil from DIM is actively being built.
In November, the following works were performed at the construction site:
Section 3:
Reinforcement of concreting of vertical structures up to -0.000 - 75%
Section 4:
Reinforcement of concreting of vertical structures (lower part) up to -0.000 – 60%
Reinforcement of the concreting of the floor slab of the lower part of room -4950 - 25%
Section 5:
Backfilling, compaction of the foundation, preparation of the area of the section for the installation of the power plate - 50%
Reinforcement of concreting of intakes in the underground part - 75%
Reinforcement of concreting of the power plate - 75%
Installation of the channel of the underground part of the EO - 100%
Parking, 1st zone:
Sealing the reasonableness of preparation for setting up the power plate - 20%
Installation of a power plate - 20%
Parking, II zone:
Setting the intake reinforcement - 30%
Wall reinforcement - 25%