Construction progress for November 2023

21.11.2023

Go back

OLEGIV Podil from DIM is actively being built.

In November, the following works were performed at the construction site:

Section 3:

  • Reinforcement of concreting of vertical structures up to -0.000 - 75%

Section 4:

  • Reinforcement of concreting of vertical structures (lower part) up to -0.000 – 60%

  • Reinforcement of the concreting of the floor slab of the lower part of room -4950 - 25%

Section 5:

  • Backfilling, compaction of the foundation, preparation of the area of the section for the installation of the power plate - 50%

  • Reinforcement of concreting of intakes in the underground part - 75%

  • Reinforcement of concreting of the power plate - 75%

  • Installation of the channel of the underground part of the EO - 100%

Parking, 1st zone:

  • Sealing the reasonableness of preparation for setting up the power plate - 20%

  • Installation of a power plate - 20%

Parking, II zone:

  • Setting the intake reinforcement - 30%

  • Wall reinforcement - 25%