Construction progress for October 2023
24.10.2023
Go back
Club house OLEGIV Podil from the company DIM is under construction.
In October, the following works were performed at the construction site:
Section 4:
Reinforcement of concrete slab - 90%
Reinforcement of concreting of the vertical structures of the walls of the underground part - 35%
Section 5:
Concreting reinforcement of the EO channel in the underground part - 85%
Concreting reinforcement of strip grid - 100%
Reinforcement of concreting of the vertical structures of the walls of the underground part - 45%
Parking:
Concreting reinforcement of the channel in the underground part - 100%
Preparation of the area of the section for the installation of foundations - 52%
Concreting the foundations of the grills - 50%