Construction progress for May 2026

01.06.2026

Go back

In May 2026, the following works were completed at the construction site:

Section 1:

  • Facade installation – 58%
  • Waterproofing of terraces on the 6th, 7th, and 8th floors (waterproofing, insulation, screed) – 100%
  • Finishing of common areas according to the design project (3rd floor) – 30%
  • Plastering of common area walls on the 2nd and 4th floors – 75%
  • Installation of insulation and reinforcement of ventilation shafts on the roof – 85%
  • Waterproofing of roof ventilation shafts – 100%
  • Brickwork of the stylobate section – 100%
  • Installation of cable networks on walls prior to plastering in common areas – 90%

Section 2:

  • Facade installation – 40%
  • Waterproofing of terraces (waterproofing, insulation, screed) – 100%
  • Insulation of roof ventilation shafts – 95%
  • Brickwork of the stylobate section – 100%

Section 3:

  • Facade installation – 48%
  • Insulation of roof ventilation shafts – 95%
  • Brickwork of the stylobate section – 100%
  • Installation of decorative facade elements (rustication) – 35%

Section 4:

  • Facade installation – 38%
  • Waterproofing of terraces (waterproofing, insulation, screed) – 100%
  • Insulation of roof ventilation shafts – 95%
  • Brickwork of the stylobate section – 95%
  • Final terrace paving (FEM paving blocks) – 20%

Section 5:

  • Facade installation – 38%
  • Terrace construction on the 6th, 7th, and 8th floors (waterproofing, insulation, screed) – 100%
  • Installation of insulation and reinforcement of roof ventilation shafts – 85%

Parking Garage:

  • Installation of K1/K2 systems (stormwater drainage and sewerage) – 80%
  • Brickwork of walls and partitions – 90%
  • Brickwork of the stylobate section (lobby exit) – 80%
  • Installation of parking garage ceiling insulation – 80%
  • Brickwork of technical rooms (ITP, ventilation chamber, electrical room) – 100%
  • Cement-sand screed (elevator lobby, ventilation chamber, security room) – 80%
  • Wall plastering (elevator lobby, ventilation chamber, security room, parking garage walls) – 20%