Construction Progress for August 2026
03.09.2026
Go back
In August 2026, the following works were carried out at the construction site:
Section 1:
- Facade works – 68%
- Facade works on the terraces of the 6th, 7th and 8th floors – 72%
- Waterproofing of the first-floor terrace – 20%
- Installation of apartment entrance doors from the 1st to the 8th floor – 90%
- Tiling of balconies – 12%
Section 2:
- Facade works – 55%
- Plastering of common-area walls from the 1st to the 8th floor – 98%
- Tiling of balconies – 10%
- Embedding of utility pipelines (K1, V1, K2) in floor slabs – 5%
Section 3:
- Installation of apartment entrance doors from the 1st to the 8th floor – 90%
- Installation of electrical cable networks (DSHK) – 95%
- Plastering of common-area walls from the 1st to the 8th floor – 98%
- Embedding of utility pipelines (K1, V1, K2) in floor slabs – 90%
Section 4:
- Installation of apartment entrance doors from the 1st to the 8th floor – 90%
- Waterproofing of the first-floor terrace – 20%
- Facade works – 46%
- Tiling of balconies – 10%
- Installation of fire protection system cable networks – 100%
Section 5:
- Facade works on the terraces of the 6th, 7th and 8th floors – 30%
- Plastering of common-area walls from the 1st to the 8th floor – 80%
- Waterproofing of the first-floor terrace – 15%
- Installation of apartment entrance doors from the 1st to the 8th floor – 80%
- Tiling of balconies – 10%
Parking:
- Installation of expansion joints on vertical structures – 85%
- Installation of air ducts – 45%
- Preparation of wall surfaces for painting – 10%
- Installation of water supply systems – 65%