Construction Progress for August 2026

03.09.2026

Go back

In August 2026, the following works were carried out at the construction site:

Section 1:

  • Facade works – 68%
  • Facade works on the terraces of the 6th, 7th and 8th floors – 72%
  • Waterproofing of the first-floor terrace – 20%
  • Installation of apartment entrance doors from the 1st to the 8th floor – 90%
  • Tiling of balconies – 12%

Section 2:

  • Facade works – 55%
  • Plastering of common-area walls from the 1st to the 8th floor – 98%
  • Tiling of balconies – 10%
  • Embedding of utility pipelines (K1, V1, K2) in floor slabs – 5%

Section 3:

  • Installation of apartment entrance doors from the 1st to the 8th floor – 90%
  • Installation of electrical cable networks (DSHK) – 95%
  • Plastering of common-area walls from the 1st to the 8th floor – 98%
  • Embedding of utility pipelines (K1, V1, K2) in floor slabs – 90%

Section 4:

  • Installation of apartment entrance doors from the 1st to the 8th floor – 90%
  • Waterproofing of the first-floor terrace – 20%
  • Facade works – 46%
  • Tiling of balconies – 10%
  • Installation of fire protection system cable networks – 100%

Section 5:

  • Facade works on the terraces of the 6th, 7th and 8th floors – 30%
  • Plastering of common-area walls from the 1st to the 8th floor – 80%
  • Waterproofing of the first-floor terrace – 15%
  • Installation of apartment entrance doors from the 1st to the 8th floor – 80%
  • Tiling of balconies – 10%

Parking:

  • Installation of expansion joints on vertical structures – 85%
  • Installation of air ducts – 45%
  • Preparation of wall surfaces for painting – 10%
  • Installation of water supply systems – 65%