Construction progress for March 2026

02.04.2026

Go back

In March 2026, the following works were carried out at the construction site:

Section 1:

  • Facade installation - 27%
  • Waterproofing of ventilation shafts on the roof - 95%
  • Installation of cement-sand screed on the 1st floor - 95%
  • Brickwork of residential premises according to the design project on the 1st floor - 95%
  • Insulation of ventilation shafts on the roof - 15%

Section 2:

  • Waterproofing of ventilation shafts on the roof - 95%
  • Installation of cement-sand screed on the 1st floor - 95%
  • Brickwork of residential premises according to the design project on the 1st floor - 95%
  • Insulation of ventilation shafts on the roof - 15%

Section 3:

  • Facade installation - 25%
  • Installation of engineering networks (V1, T3, OV, ETR) on the floor - 75%
  • Installation of facade tiles - 75%
  • Waterproofing of ventilation shafts on the roof - 95%
  • Installation of cement-sand screed on the 1st floor - 95%
  • Brickwork of residential premises according to the design project on the 1st floor - 95%
  • Insulation of ventilation shafts on the roof - 55%
  • Installation of ventilation equipment on the roof - 35%

Section 4:

  • Waterproofing of ventilation shafts on the roof - 95%
  • Brickwork of residential premises according to the design project on the 1st floor - 95%
  • Insulation of ventilation shafts on the roof - 55%

Section 5:

  • Terrace construction on floors 6-8 (waterproofing, insulation, screed) - 65%
  • Waterproofing of ventilation shafts on the roof - 95%
  • Brickwork of residential premises according to the design project on the 1st floor - 95%
  • Insulation of ventilation shafts on the roof - 55%

Parking:

  • Installation of K1/K2 (drainage, sewerage) - 15%
  • Brickwork of walls and partitions - 5%
  • Brickwork of the stylobate part - 50%