Construction progress for April 2024
24.04.2024
Go back
LUCKY LAND by DIM is under construction.
We share the latest news from the construction site for April:
Building No. 3, Section 1:
- installation of access control systems;
- setting up the navigation system.
Building No. 3, Section 2:
- installation of access control systems;
- setting up the navigation system.
Building No. 3, Section 3:
- installation of access control systems;
- setting up the navigation system.
Improvements, building No. 3:
- arrangement of outdoor lighting;
- landscaping of the territory continues.
Building No. 4, Section 1:
- installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
- arrangement of apartment wiring of water supply systems;
- arrangement of risers and apartment wiring of EO systems;
- installation of elevator equipment;
- waterproofing of the terraces continues;
- installation of floor screeds in apartments and MZK 5-9 floors;
- arrangement of walls and partitions - 1st and 1st floors.
Building No. 4, Section 2:
- installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
- installation of elevator equipment;
- waterproofing of the terraces continues;
- installation of floor screeds in apartments and MZK 4-9 floors;
- arrangement of walls and partitions - 1st and 1st floors.
Building No. 4, Section 3:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- arrangement of facades;
- work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
- installation of elevator equipment;
- waterproofing of the terraces continues;
- arrangement of walls and partitions - 1st and 1st floors.
Building No. 5, Section 1:
- arrangement of vertical and horizontal elements of monolithic frame 11, 12 floors;
- construction of walls and partitions on the 3rd, 6th, 7th, and 8th floors continues;
- installation of ventilation units on the 9th and 10th floors continues;
- the installation of staircases and landings on the 10th and 11th floors continues.
Building No. 5, Section 2:
- arrangement of vertical and horizontal elements of monolithic frame 10, 11 floors;
- construction of walls and partitions on the 3rd, 4th, 6th, and 7th floors continues;
- the installation of ventilation units on the 8th and 9th floors continues;
- the installation of staircases and landings on the 9th floor continues.
Building No. 5, Section 3:
- arrangement of vertical and horizontal elements of monolithic frame 6, 7 floors;
- installation of staircases and landings on the 5th and 6th floors;
- installation of vertical waterproofing;
- installation of ventilation units on the 2nd and 3rd floors continues.
Building No. 5, section 1.6 (parking adjacent to section 3):
- installation of a monolithic ramp slab
- work on installation of vertical waterproofing continues;
- arrangement of walls and partitions of TP.
Building No. 5, section 1.5 (parking adjacent to sections 1-2):
- work continues on the installation of vertical elements of the monolithic frame.
Building No. 6, Section 1:
- arrangement of walls and partitions - 1st floor.
Building No. 6, Section 2:
- preparation of elevator shafts for installation of elevators.