LUCKY LAND by DIM is under construction.

We share the latest news from the construction site for April:

Building No. 3, Section 1:

  • installation of access control systems;
  • setting up the navigation system.

Building No. 3, Section 2:

  • installation of access control systems;
  • setting up the navigation system.

Building No. 3, Section 3:

  • installation of access control systems;
  • setting up the navigation system.

Improvements, building No. 3:

  • arrangement of outdoor lighting;
  • landscaping of the territory continues.

Building No. 4, Section 1:

  • installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
  • arrangement of apartment wiring of water supply systems;
  • arrangement of risers and apartment wiring of EO systems;
  • installation of elevator equipment;
  • waterproofing of the terraces continues;
  • installation of floor screeds in apartments and MZK 5-9 floors;
  • arrangement of walls and partitions - 1st and 1st floors.

Building No. 4, Section 2:

  • installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
  • installation of elevator equipment;
  • waterproofing of the terraces continues;
  • installation of floor screeds in apartments and MZK 4-9 floors;
  • arrangement of walls and partitions - 1st and 1st floors.

Building No. 4, Section 3:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • arrangement of facades;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment;
  • waterproofing of the terraces continues;
  • arrangement of walls and partitions - 1st and 1st floors.

Building No. 5, Section 1:

  • arrangement of vertical and horizontal elements of monolithic frame 11, 12 floors;
  • construction of walls and partitions on the 3rd, 6th, 7th, and 8th floors continues;
  • installation of ventilation units on the 9th and 10th floors continues;
  • the installation of staircases and landings on the 10th and 11th floors continues.

Building No. 5, Section 2:

  • arrangement of vertical and horizontal elements of monolithic frame 10, 11 floors;
  • construction of walls and partitions on the 3rd, 4th, 6th, and 7th floors continues;
  • the installation of ventilation units on the 8th and 9th floors continues;
  • the installation of staircases and landings on the 9th floor continues.

Building No. 5, Section 3:

  • arrangement of vertical and horizontal elements of monolithic frame 6, 7 floors;
  • installation of staircases and landings on the 5th and 6th floors;
  • installation of vertical waterproofing;
  • installation of ventilation units on the 2nd and 3rd floors continues.

Building No. 5, section 1.6 (parking adjacent to section 3):

  • installation of a monolithic ramp slab
  • work on installation of vertical waterproofing continues;
  • arrangement of walls and partitions of TP.

Building No. 5, section 1.5 (parking adjacent to sections 1-2):

  • work continues on the installation of vertical elements of the monolithic frame.

Building No. 6, Section 1:

  • arrangement of walls and partitions - 1st floor.

Building No. 6, Section 2:

  • preparation of elevator shafts for installation of elevators.