Construction progress for February 2024
27.02.2024
Go back
LUCKY LAND by DIM is under construction. The 3rd building is put into operation!
We share the latest news from the construction site for February:
Building No. 3, Section 1:
- arrangement of equipment input group;
- arrangement of equipment of public places;
- installation of access control systems;
- arranging the floor covering in the passenger elevator from porcelain stoneware;
- installation of thermal curtains (input group);
- setting up the navigation system.
Building No. 3, Section 2:
- arrangement of equipment of public places;
- arrangement of equipment input group;
- installation of access control systems;
- arrangement of floor covering in passenger and freight elevators from porcelain stoneware;
- setting up the navigation system.
Building No. 3, Section 3:
- arrangement of equipment of public places;
- arrangement of equipment input group;
- installation of access control systems;
- arrangement of floor covering in passenger and freight elevators from porcelain stoneware;
- setting up the navigation system.
Improvements, building No. 3:
- arrangement of outdoor lighting;
- arranging a fence;
- landscaping of the territory continues.
Building No. 4, Section 1:
- installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
- arrangement of apartment wiring of water supply systems;
- arrangement of risers and apartment wiring of EO systems;
- installation of elevator equipment;
- waterproofing of the terraces on the 3rd and 9th floors continues.
Building No. 4, Section 2:
- installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
- installation of elevator equipment;
- waterproofing of the terraces on the 3rd and 9th floors continues.
Building No. 4, Section 3:
- installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
- arrangement of facades;
- work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
- installation of elevator equipment;
- installation of waterproofing of the terraces on the 3rd floor.
Building No. 5, Section 1:
- arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
- arrangement of walls and partitions 3, 4, 6 floors;
- installation of ventilation units 6, 7, 8 floors;
- installation of staircases and landings on the 10th and 11th floors.
Building No. 5, Section 2:
- arrangement of vertical elements of the monolithic frame on the 10th floor;
- arrangement of walls and partitions 3, 4, 5, 6 floors;
- installation of ventilation units 6, 7, 8 floors;
- installation of staircases and landings on the 8th floor.
Building No. 5, Section 3:
- arrangement of vertical and horizontal elements of monolithic frame 1, 2, 3 floors;
- arrangement of monolithic stairs - 1st floor;
- installation of staircases and landings on the 1st floor;
- installation of vertical waterproofing.
Building No. 5, section 1.6 (parking adjacent to section 3):
- arrangement of the floor slab;
- installation of vertical waterproofing;
- backfilling of the underground part.
Building No. 5, section 1.5 (parking adjacent to sections 1-2):
- arrangement of vertical elements of a monolithic frame.
Building No. 6, Section 2:
- installation of PVC structures 4, 5, 6, 7, 8 floors.