LUCKY LAND by DIM is under construction.

We share the latest news from the construction site for June:

Improvements, building No. 3:

  • arrangement of outdoor lighting;
  • landscaping of the territory continues;
  • landscaping (bicycle path).

Building No. 4, Section 1:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • installation of screeds in apartments and MZK from the 9th to the 13th floor;
  • work on plastering of the MZK has begun;
  • arrangement of risers and apartment wiring of EO systems;
  • completed works on the installation of apartment-by-apartment distribution of water supply and heating systems from the 3rd to the 13th floor;
  • installation of elevator equipment;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • decoration of facades.

Building No. 4, Section 2:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • completed works on the installation of apartment-by-apartment distribution of water supply and heating systems from the 3rd to the 13th floor;
  • installation of screeds in apartments and MZK from the 9th to the 13th floor;
  • arrangement of risers and apartment wiring of EO systems;
  • installation of elevator equipment;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • decoration of facades

Building No. 4, Section 3:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • arrangement of facades;
  • work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
  • installation of elevator equipment;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • preparatory work for the installation of apartment networks of heating, water supply and electricity supply from the 3rd to the 13th floor;
  • preparatory work for the installation of the screed from the 3rd to the 13th floor.

House No. 4 external networks:

  • arrangement of external networks B1, K1, K2.

Building No. 5, Section 1:

  • arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
  • arrangement of walls and partitions 6th, 8th, 9th floors;
  • installation of staircases and landings on the 11th and 12th floors;
  • arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
  • arrangement of walls and partitions 6th, 8th, 9th floors;
  • the installation of staircases and landings on the 10th floor continues.

Building No. 5, Section 2:

  • arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
  • construction of walls and partitions on the 6th, 8th, and 9th floors continues;
  • installation of staircases and landings on the 10th floor.

Building No. 5, Section 3:

  • arrangement of vertical and horizontal elements of monolithic frame 7, 8 floors;
  • installation of staircases and landings on the 5th, 6th, 7th floor;
  • installation of vertical waterproofing;
  • installation of ventilation units on 4.5 floors continues.

Building No. 5, section 1.6 (parking adjacent to section 3):

  • work on installation of vertical waterproofing continues;
  • arrangement of solid brick walls in TP.

Building No. 5, section 1.5 (parking adjacent to sections 1-2):

  • installation of vertical waterproofing.

Building No. 6, Section 1:

  • installation of walls and partitions in the basement.

Building No. 6, Section 2:

  • arrangement of walls and partitions in the basement;
  • preparation of elevator shafts for installation of elevators, grinding.