Construction progress for June 2024
26.06.2024
Go back
LUCKY LAND by DIM is under construction.
We share the latest news from the construction site for June:
Improvements, building No. 3:
- arrangement of outdoor lighting;
- landscaping of the territory continues;
- landscaping (bicycle path).
Building No. 4, Section 1:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- installation of screeds in apartments and MZK from the 9th to the 13th floor;
- work on plastering of the MZK has begun;
- arrangement of risers and apartment wiring of EO systems;
- completed works on the installation of apartment-by-apartment distribution of water supply and heating systems from the 3rd to the 13th floor;
- installation of elevator equipment;
- waterproofing of the terraces on the 3rd and 9th floors continues;
- decoration of facades.
Building No. 4, Section 2:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- completed works on the installation of apartment-by-apartment distribution of water supply and heating systems from the 3rd to the 13th floor;
- installation of screeds in apartments and MZK from the 9th to the 13th floor;
- arrangement of risers and apartment wiring of EO systems;
- installation of elevator equipment;
- waterproofing of the terraces on the 3rd and 9th floors continues;
- decoration of facades
Building No. 4, Section 3:
- installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
- arrangement of facades;
- work on the decoration of technical superstructures and ventilation shafts on the roof is being carried out;
- installation of elevator equipment;
- waterproofing of the terraces on the 3rd and 9th floors continues;
- preparatory work for the installation of apartment networks of heating, water supply and electricity supply from the 3rd to the 13th floor;
- preparatory work for the installation of the screed from the 3rd to the 13th floor.
House No. 4 external networks:
- arrangement of external networks B1, K1, K2.
Building No. 5, Section 1:
- arrangement of vertical and horizontal elements of the monolithic frame on the 12th floor;
- arrangement of walls and partitions 6th, 8th, 9th floors;
- installation of staircases and landings on the 11th and 12th floors;
- arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
- arrangement of walls and partitions 6th, 8th, 9th floors;
- the installation of staircases and landings on the 10th floor continues.
Building No. 5, Section 2:
- arrangement of vertical and horizontal elements of the monolithic frame on the 11th floor;
- construction of walls and partitions on the 6th, 8th, and 9th floors continues;
- installation of staircases and landings on the 10th floor.
Building No. 5, Section 3:
- arrangement of vertical and horizontal elements of monolithic frame 7, 8 floors;
- installation of staircases and landings on the 5th, 6th, 7th floor;
- installation of vertical waterproofing;
- installation of ventilation units on 4.5 floors continues.
Building No. 5, section 1.6 (parking adjacent to section 3):
- work on installation of vertical waterproofing continues;
- arrangement of solid brick walls in TP.
Building No. 5, section 1.5 (parking adjacent to sections 1-2):
- installation of vertical waterproofing.
Building No. 6, Section 1:
- installation of walls and partitions in the basement.
Building No. 6, Section 2:
- arrangement of walls and partitions in the basement;
- preparation of elevator shafts for installation of elevators, grinding.