Construction progress for August 2025
03.09.2025
Go back
Sharing fresh news from the construction site for August:
Building #3, parking:
- installation of polymer floor coating for parking - 100%.
Building #3, landscaping:
- landscaping of the inner courtyard - 95%.
Building #4:
- installation of parking exhaust and inlet systems - 35%;
- landscaping of the territory - 18%;
- installation of low-voltage networks (SCD, SPZ, SPS, SCG) - 60%.
Building #4, section 1:
- installation of brickwork on the first floor - 100%;
- plastering of walls in the lobby - 100%;
- installation of entry group SPOK - 50%;
- installation of windows (VR-1) - 100%;
- installation of heating systems in non-residential premises - 50%;
- drilling holes for radiators in apartments - 95%.
Building #4, section 2:
- installation of translucent protective structures (SPOK) of the entrance group - 95%;
- installation of heating systems in non-residential premises - 50%;
- installation of distribution cabinets from 3rd to 13th floor - 100%;
- electrical and low-voltage works in the lobby - 45%;
- installation of windows (VR-29) - 85%.
Building #4, section 3:
- installation of translucent protective structures (SPOK) of the entrance group - 95%;
- installation of smoke detectors in apartments - 100%;
- installation of doors in technical rooms - 100%;
- installation of heating systems in non-residential premises - 50%;
- installation of distribution cabinets from 3rd to 13th floor - 100%;
- installation of smoke exhaust valves in apartments - 80%;
- drilling holes for radiators in apartments - 50%;
- masonry of partitions on the first floor - 100%.
Building #5, section 3:
- installation of walls and partitions on the 9th floor - 25%;
- masonry of ventilation ducts on the roof - 10%;
- masonry of walls and partitions in the basement - 15%;
- installation of metal brackets for brickwork - 65%.
Building #6, section 1:
- facade construction - 20%.
Building #6, section 2:
- facade construction - 85%.