Construction progress for August 2025

03.09.2025

Go back

Sharing fresh news from the construction site for August:

Building #3, parking:

  • installation of polymer floor coating for parking - 100%.

Building #3, landscaping:

  • landscaping of the inner courtyard - 95%.

Building #4:

  • installation of parking exhaust and inlet systems - 35%;
  • landscaping of the territory - 18%;
  • installation of low-voltage networks (SCD, SPZ, SPS, SCG) - 60%.

Building #4, section 1:

  • installation of brickwork on the first floor - 100%;
  • plastering of walls in the lobby - 100%;
  • installation of entry group SPOK - 50%;
  • installation of windows (VR-1) - 100%;
  • installation of heating systems in non-residential premises - 50%;
  • drilling holes for radiators in apartments - 95%.

Building #4, section 2:

  • installation of translucent protective structures (SPOK) of the entrance group - 95%;
  • installation of heating systems in non-residential premises - 50%;
  • installation of distribution cabinets from 3rd to 13th floor - 100%;
  • electrical and low-voltage works in the lobby - 45%;
  • installation of windows (VR-29) - 85%.

Building #4, section 3:

  • installation of translucent protective structures (SPOK) of the entrance group - 95%;
  • installation of smoke detectors in apartments - 100%;
  • installation of doors in technical rooms - 100%;
  • installation of heating systems in non-residential premises - 50%;
  • installation of distribution cabinets from 3rd to 13th floor - 100%;
  • installation of smoke exhaust valves in apartments - 80%;
  • drilling holes for radiators in apartments - 50%;
  • masonry of partitions on the first floor - 100%.

Building #5, section 3:

  • installation of walls and partitions on the 9th floor - 25%;
  • masonry of ventilation ducts on the roof - 10%;
  • masonry of walls and partitions in the basement - 15%;
  • installation of metal brackets for brickwork - 65%.

Building #6, section 1:

  • facade construction - 20%.

Building #6, section 2:

  • facade construction - 85%.