LUCKY LAND
Construction progress for December 2025

05.01.2026

Go back

Sharing fresh news from the construction site for December:

Building №3, parking:

  • installation of road signs and road markings - 100%

Building №3, landscaping:

  • installation of automatic irrigation system - 90%

Building №4:

  • landscaping on Berkovetska street - 30%

Building №4, section 1:

  • installation of ceramic tiles on the stair landing - 100%
  • installation of connections (SPD) - 85%
  • installation of SPS_SO and SPZ systems in commercial premises - 80%
  • facade installation - 89%
  • painting walls and ceilings on stair landings - 75%
  • installation of covers (SPD) - 90%

Building №4, section 2:

  • installation of connections (SPD) - 85%
  • installation of covers (SPD) - 90%
  • installation of ventilation systems in commercial premises - 100%
  • installation of SPS_SO and SPZ systems in commercial premises - 95%
  • facade installation - 75%

Building №4, section 3:

  • installation of connections (SPD) - 90%
  • installation of SPS systems in the lobby - 100%
  • installation of SPS_SO and SPZ systems in commercial premises - 95%
  • installation of decorative plaster in MZK on the 3rd floor - 90%, on the 4th floor - 60%
  • installation of ventilation systems in commercial premises - 85%

Building №5, section 1:

  • masonry of walls and partitions in the basement - 85%

Building №5, section 2:

  • masonry of walls and partitions in the basement - 25%

Building №6, section 1:

  • facade installation - 34%
  • insulation of balconies in apartments - 60%
  • installation of K2 riser systems - 100%

Building №6, section 2:

  • facade installation - 96%
  • installation of covers in ventilation shafts - 100%