Sharing fresh news from the construction site for September:

Building №3, parking:

  • decorating walls and columns - 30%

Building №3, landscaping:

  • installation of decorative lighting - 85%

Building №4:

  • landscaping of the territory - 20%
  • laying cables for ACS systems - 100%

Building №4, section 1:

  • application of decorative plaster in apartments 5, 6, 7, 8 - 90%
  • installation of curvilinear fencing structures (SPOK) - 15%
  • laying cables for ACS systems - 85%
  • installation of aluminum trims at the entrances - 100%

Building №4, section 2:

  • installation of ceramic skirting in apartments 7 to 13 - 70%
  • installation of curvilinear fencing structures (SPOK) - 35%
  • laying cables for ACS systems - 85%
  • installation of aluminum trims at the entrances - 100%

Building №4, section 3:

  • installation of curvilinear fencing structures (SPOK) - 25%
  • installation of aluminum trims at the entrances - 100%

Building №5, section 1:

  • masonry of walls and partitions in the basement - 47%

Building №5, section 3:

  • masonry of ventilation ducts on the roof - 80%
  • masonry of walls and partitions in the basement - 60%

Building №6, section 1:

  • facade installation - 25%