Construction progress in September 2025
01.10.2025
Go back
Sharing fresh news from the construction site for September:
Building №3, parking:
- decorating walls and columns - 30%
Building №3, landscaping:
- installation of decorative lighting - 85%
Building №4:
- landscaping of the territory - 20%
- laying cables for ACS systems - 100%
Building №4, section 1:
- application of decorative plaster in apartments 5, 6, 7, 8 - 90%
- installation of curvilinear fencing structures (SPOK) - 15%
- laying cables for ACS systems - 85%
- installation of aluminum trims at the entrances - 100%
Building №4, section 2:
- installation of ceramic skirting in apartments 7 to 13 - 70%
- installation of curvilinear fencing structures (SPOK) - 35%
- laying cables for ACS systems - 85%
- installation of aluminum trims at the entrances - 100%
Building №4, section 3:
- installation of curvilinear fencing structures (SPOK) - 25%
- installation of aluminum trims at the entrances - 100%
Building №5, section 1:
- masonry of walls and partitions in the basement - 47%
Building №5, section 3:
- masonry of ventilation ducts on the roof - 80%
- masonry of walls and partitions in the basement - 60%
Building №6, section 1:
- facade installation - 25%