Construction progress in October 2025
05.11.2025
Go back
Sharing fresh news from the construction site for October:
Building №3, parking:
- wall and column decoration - 85%
Building №4:
- landscaping progress - 22%
- installation of ventilation and supply systems - 45%
Building №4, section 1:
- decorative plaster application in common areas from 9th to 13th floor - 90%
- installation of curved fencing structures (SPAC) - 90%
Building №4, section 2:
- staircase decoration - 80%
- installation of curved fencing structures (SPAC) - 100%
- painting of gypsum board ceilings in common areas from 3rd to 13th floor - 75%
Building №4, section 3:
- installation of curved fencing structures (SPAC) - 90%
- installation of smoke extraction valves on the roof - 35%
Building №5, section 1:
- masonry of walls and partitions in the basement - 70%
Building №5, section 3:
- masonry of ventilation ducts on the roof - 100%
- masonry of walls and partitions in the basement - 70%
- installation of ventilation covers - 100%
Building №6, section 1:
- facade construction - 30%