LUCKY LAND
Construction progress in October 2025

05.11.2025

Go back

Sharing fresh news from the construction site for October:

Building №3, parking:

  • wall and column decoration - 85%

Building №4:

  • landscaping progress - 22%
  • installation of ventilation and supply systems - 45%

Building №4, section 1:

  • decorative plaster application in common areas from 9th to 13th floor - 90%
  • installation of curved fencing structures (SPAC) - 90%

Building №4, section 2:

  • staircase decoration - 80%
  • installation of curved fencing structures (SPAC) - 100%
  • painting of gypsum board ceilings in common areas from 3rd to 13th floor - 75%

Building №4, section 3:

  • installation of curved fencing structures (SPAC) - 90%
  • installation of smoke extraction valves on the roof - 35%

Building №5, section 1:

  • masonry of walls and partitions in the basement - 70%

Building №5, section 3:

  • masonry of ventilation ducts on the roof - 100%
  • masonry of walls and partitions in the basement - 70%
  • installation of ventilation covers - 100%

Building №6, section 1:

  • facade construction - 30%