Construction progress for April 2025
02.05.2025
Go back
Sharing fresh news from the construction site for April:
Building №3, parking:
- laying polymer floor coating in the parking lot 1500 m2.
Building №3, improvement:
- continuing improvement of the inner courtyard;
- improvement of the area near the sales department.
Building №4:
- installation of smoke extraction and parking ventilation systems;
- improvement of the area;
- installation of fire alarm and fire extinguishing systems;
- installation of water supply and sewerage systems;
- installation of transformer substation-5;
- electrical installation works in the parking lot;
- roof installation in the parking.
Building №4, section 1:
- painting GKL ceiling in MZK;
- decorating facades with LMM;
- continuing masonry works on the 1st and 2nd floors;
- installation of smoke extraction and ventilation systems;
- installation of PVC structures on the stylobate part;
- continuing finishing works in technical rooms (wall painting, ceiling insulation);
- installation of fire alarm and fire extinguishing systems in technical rooms;
- continuing installation of hatches in MZK from 3rd to 13th floors;
- installation of radiators in apartments;
- preparatory works for finishing the staircases;
- installation of bike path.
Building №4, section 2:
- decorating facades with LMM;
- painting GKL ceiling in MZK;
- continuing masonry works on the 1st and 2nd floors;
- installation of transparent light structures (SPOK);
- continuing finishing works in technical rooms (wall painting, ceiling insulation);
- continuing installation of hatches in MZK from 3rd to 13th floors;
- preparatory works for finishing the staircases;
- installation of bike path.
Building №4, section 3:
- painting GKL ceiling in MZK;
- installation of smoke extraction and ventilation systems;
- installation of transparent light structures (SPOK);
- continuing finishing works in technical rooms (wall painting, ceiling insulation);
- continuing electrical installation works from 9th to 13th floors;
- installation of entrance doors from 3rd to 13th floors;
- preparatory works for finishing the staircases.
Building №5, section 1:
- installation of walls and partitions on 1st, 2nd and 13th floors;
- installation of vertical elements of the monolithic parapet.
Building №5, section 2:
- installation of walls and partitions on 1st and 2nd floors, roof.
Building №5, section 3:
- installation of walls and partitions on 1st, 3rd, 7th floors;
- installation of parking lot roof.
Building №6, section 1:
- installation of brackets for air conditioner units;
- continuing installation of metal-plastic window structures on 12th, 13th, 14th floors;
- facade improvement with LMM.
Building №6, section 2:
- facade improvement with LMM;
- installation of brackets for air conditioner units.