Lucky Land
Construction progress for April 2025

02.05.2025

Go back

Sharing fresh news from the construction site for April:

Building №3, parking:

  • laying polymer floor coating in the parking lot 1500 m2.

Building №3, improvement:

  • continuing improvement of the inner courtyard;
  • improvement of the area near the sales department.

Building №4:

  • installation of smoke extraction and parking ventilation systems;
  • improvement of the area;
  • installation of fire alarm and fire extinguishing systems;
  • installation of water supply and sewerage systems;
  • installation of transformer substation-5;
  • electrical installation works in the parking lot;
  • roof installation in the parking.

Building №4, section 1:

  • painting GKL ceiling in MZK;
  • decorating facades with LMM;
  • continuing masonry works on the 1st and 2nd floors;
  • installation of smoke extraction and ventilation systems;
  • installation of PVC structures on the stylobate part;
  • continuing finishing works in technical rooms (wall painting, ceiling insulation);
  • installation of fire alarm and fire extinguishing systems in technical rooms;
  • continuing installation of hatches in MZK from 3rd to 13th floors;
  • installation of radiators in apartments;
  • preparatory works for finishing the staircases;
  • installation of bike path.

Building №4, section 2:

  • decorating facades with LMM;
  • painting GKL ceiling in MZK;
  • continuing masonry works on the 1st and 2nd floors;
  • installation of transparent light structures (SPOK);
  • continuing finishing works in technical rooms (wall painting, ceiling insulation);
  • continuing installation of hatches in MZK from 3rd to 13th floors;
  • preparatory works for finishing the staircases;
  • installation of bike path.

Building №4, section 3:

  • painting GKL ceiling in MZK;
  • installation of smoke extraction and ventilation systems;
  • installation of transparent light structures (SPOK);
  • continuing finishing works in technical rooms (wall painting, ceiling insulation);
  • continuing electrical installation works from 9th to 13th floors;
  • installation of entrance doors from 3rd to 13th floors;
  • preparatory works for finishing the staircases.

Building №5, section 1:

  • installation of walls and partitions on 1st, 2nd and 13th floors;
  • installation of vertical elements of the monolithic parapet.

Building №5, section 2:

  • installation of walls and partitions on 1st and 2nd floors, roof.

Building №5, section 3:

  • installation of walls and partitions on 1st, 3rd, 7th floors;
  • installation of parking lot roof.

Building №6, section 1:

  • installation of brackets for air conditioner units;
  • continuing installation of metal-plastic window structures on 12th, 13th, 14th floors;
  • facade improvement with LMM.

Building №6, section 2:

  • facade improvement with LMM;
  • installation of brackets for air conditioner units.