Construction progress for February 2025
06.03.2025
Go back
Sharing fresh updates from the construction site for February:
Building №3, Parking:
- Installation of a polymer floor coating in the parking area.
Building №3, Landscaping:
- Continued work on the landscaping of the inner courtyard.
Building №4:
- Installation of smoke extraction and ventilation systems in the parking area;
- Landscaping works in progress;
- Installation of ASPG and SPZ systems;
- Installation of VK systems.
Building №4, Section 1:
- Installation of SPZ systems in technical premises;
- Installation of doors in storage rooms;
- Finishing of MZK from the 3rd to the 13th floor (junctions with fire dampers);
- Facade finishing of LMM;
- Brickwork of the 1st and 2nd floors;
- Installation of smoke extraction and ventilation systems;
- Installation of PVC structures in the stylobate part;
- Finishing of technical premises (wall painting, ceiling insulation);
- Installation of hatches in MZK from the 3rd to the 13th floor.
Building №4, Section 2:
- Facade finishing of LMM;
- Finishing of MZK from the 3rd to the 13th floor (installation and painting of the gypsum board ceiling);
- Brickwork of the 1st and 2nd floors;
- Finishing of technical premises (wall painting, ceiling insulation);
- Continued installation of transparent enclosing structures (SPOK);
- Installation of PVC structures in the stylobate part;
- Installation of hatches in MZK from the 3rd to the 13th floor.
Building №4, Section 3:
- Installation of a gypsum board ceiling in MZK from the 3rd to the 13th floor;
- Installation of smoke extraction and ventilation systems;
- Installation of transparent enclosing structures (SPOK);
- Installation of SPZ systems from the 3rd to the 6th floor;
- Finishing of technical premises (wall painting, ceiling insulation);
- Electrical installation works from the 9th to the 13th floor;
- Installation of entrance apartment doors from the 3rd to the 13th floor.
Transformer Substation №5:
- Installation of the foundation and vertical monolithic structures.
Building №5, Section 1:
- Construction of walls and partitions on the 12th floor;
- Installation of the stylobate structure on the 1st floor;
- Installation of vertical elements of the monolithic frame on the 14th floor.
Building №5, Section 2:
- Construction of walls and partitions on the 12th floor;
- Installation of the stylobate structure on the 1st floor.
Building №5, Section 3:
- Construction of walls and partitions on the 6th floor;
- Installation of the stylobate structure on the 1st floor.
Building №5, Parking 1.6 (parking adjacent to section 3):
- Installation of vertical and horizontal elements of the monolithic frame on the 1st level.
Building №6, Section 1:
- Ongoing installation of the passenger elevator;
- Installation of metal-plastic window structures on the 9th-11th floors.
Building №6, Section 2:
- Ongoing installation of the passenger elevator;
- Installation of the facade.