LUCKY LAND
Construction progress for February 2025

06.03.2025

Go back

Sharing fresh updates from the construction site for February:

Building №3, Parking:

  • Installation of a polymer floor coating in the parking area.

Building №3, Landscaping:

  • Continued work on the landscaping of the inner courtyard.

Building №4:

  • Installation of smoke extraction and ventilation systems in the parking area;
  • Landscaping works in progress;
  • Installation of ASPG and SPZ systems;
  • Installation of VK systems.

Building №4, Section 1:

  • Installation of SPZ systems in technical premises;
  • Installation of doors in storage rooms;
  • Finishing of MZK from the 3rd to the 13th floor (junctions with fire dampers);
  • Facade finishing of LMM;
  • Brickwork of the 1st and 2nd floors;
  • Installation of smoke extraction and ventilation systems;
  • Installation of PVC structures in the stylobate part;
  • Finishing of technical premises (wall painting, ceiling insulation);
  • Installation of hatches in MZK from the 3rd to the 13th floor.

Building №4, Section 2:

  • Facade finishing of LMM;
  • Finishing of MZK from the 3rd to the 13th floor (installation and painting of the gypsum board ceiling);
  • Brickwork of the 1st and 2nd floors;
  • Finishing of technical premises (wall painting, ceiling insulation);
  • Continued installation of transparent enclosing structures (SPOK);
  • Installation of PVC structures in the stylobate part;
  • Installation of hatches in MZK from the 3rd to the 13th floor.

Building №4, Section 3:

  • Installation of a gypsum board ceiling in MZK from the 3rd to the 13th floor;
  • Installation of smoke extraction and ventilation systems;
  • Installation of transparent enclosing structures (SPOK);
  • Installation of SPZ systems from the 3rd to the 6th floor;
  • Finishing of technical premises (wall painting, ceiling insulation);
  • Electrical installation works from the 9th to the 13th floor;
  • Installation of entrance apartment doors from the 3rd to the 13th floor.

Transformer Substation №5:

  • Installation of the foundation and vertical monolithic structures.

Building №5, Section 1:

  • Construction of walls and partitions on the 12th floor;
  • Installation of the stylobate structure on the 1st floor;
  • Installation of vertical elements of the monolithic frame on the 14th floor.

Building №5, Section 2:

  • Construction of walls and partitions on the 12th floor;
  • Installation of the stylobate structure on the 1st floor.

Building №5, Section 3:

  • Construction of walls and partitions on the 6th floor;
  • Installation of the stylobate structure on the 1st floor.

Building №5, Parking 1.6 (parking adjacent to section 3):

  • Installation of vertical and horizontal elements of the monolithic frame on the 1st level.

Building №6, Section 1:

  • Ongoing installation of the passenger elevator;
  • Installation of metal-plastic window structures on the 9th-11th floors.

Building №6, Section 2:

  • Ongoing installation of the passenger elevator;
  • Installation of the facade.