Sharing fresh updates from the construction site for July:

Building No. 3, parking:

  • ongoing works to install polymer floor coating in the parking lot - 98%.

Building No. 3, landscaping:

  • ongoing landscaping works in the inner courtyard - 75%.

Building No. 4:

  • installation of smoke removal and ventilation systems in the parking lot - 95%;
  • installation and connection of pumping station AHPS - 75%;
  • installation of exhaust and supply systems of the parking lot - 15%

Building No. 4, section 1:

  • arrangement of finishing in common areas from 3 to 13 floors (applying glass cloth to plasterboard ceilings in common areas, installation of ceramic skirting boards and wall cladding in the elevator hall with ceramic tiles) - 100%;
  • applying finishing touches in common areas from 3 to 13 floors - 10%;
  • facade decoration of LMH - 70%;
  • installation of smoke removal valves and air support in technical rooms - 45%;
  • laying low-voltage networks on the ground floor - 90%;
  • laying brickwork on the ground floor - 90%;
  • electrical works in the lobby - 95%;
  • plastering walls in the lobby - 25%;
  • installation of CPD at entrance groups - 50%;
  • installation of windows (VR-1) - 95%;
  • installation of smoke sensors in apartments - 100%.

Building No. 4, section 2:

  • arrangement of finishing in common areas from 3 to 13 floors (applying glass cloth to plasterboard ceilings in common areas, installation of ceramic skirting boards and wall cladding in the elevator hall with ceramic tiles) - 95%;
  • installation of smoke removal and ventilation systems on the ground floor - 100%;
  • installation of transparent fencing structures (CPD) at the entrance group - 65%;
  • wrapping of domestic pumping - 90%;
  • electrical and low-voltage works in the lobby - 25%;
  • installation of smoke sensors in apartments - 100%;
  • installation of CPD at entrance groups - 50%;
  • laying brickwork on the ground floor - 95%.

Building No. 4, section 3:

  • installation of metal structures for curved facade - 100%;
  • installation of CPD at entrance groups - 75%;
  • installation of smoke sensors in apartments - 25%;
  • installation of doors in technical rooms - 85%;
  • installation of low-voltage networks in the lobby - 55%.

Building No. 5, section 2:

  • construction of walls and partitions on the 1st floor - 100%.

Building No. 5, section 3:

  • construction of walls and partitions on the 10th, 11th, 12th floors - 40%.

Building No. 6, section 1:

  • facade construction - 15%.

Building No. 6, section 2:

  • facade construction - 80%.