Construction progress for July 2025
02.08.2025
Go back
Sharing fresh updates from the construction site for July:
Building No. 3, parking:
- ongoing works to install polymer floor coating in the parking lot - 98%.
Building No. 3, landscaping:
- ongoing landscaping works in the inner courtyard - 75%.
Building No. 4:
- installation of smoke removal and ventilation systems in the parking lot - 95%;
- installation and connection of pumping station AHPS - 75%;
- installation of exhaust and supply systems of the parking lot - 15%
Building No. 4, section 1:
- arrangement of finishing in common areas from 3 to 13 floors (applying glass cloth to plasterboard ceilings in common areas, installation of ceramic skirting boards and wall cladding in the elevator hall with ceramic tiles) - 100%;
- applying finishing touches in common areas from 3 to 13 floors - 10%;
- facade decoration of LMH - 70%;
- installation of smoke removal valves and air support in technical rooms - 45%;
- laying low-voltage networks on the ground floor - 90%;
- laying brickwork on the ground floor - 90%;
- electrical works in the lobby - 95%;
- plastering walls in the lobby - 25%;
- installation of CPD at entrance groups - 50%;
- installation of windows (VR-1) - 95%;
- installation of smoke sensors in apartments - 100%.
Building No. 4, section 2:
- arrangement of finishing in common areas from 3 to 13 floors (applying glass cloth to plasterboard ceilings in common areas, installation of ceramic skirting boards and wall cladding in the elevator hall with ceramic tiles) - 95%;
- installation of smoke removal and ventilation systems on the ground floor - 100%;
- installation of transparent fencing structures (CPD) at the entrance group - 65%;
- wrapping of domestic pumping - 90%;
- electrical and low-voltage works in the lobby - 25%;
- installation of smoke sensors in apartments - 100%;
- installation of CPD at entrance groups - 50%;
- laying brickwork on the ground floor - 95%.
Building No. 4, section 3:
- installation of metal structures for curved facade - 100%;
- installation of CPD at entrance groups - 75%;
- installation of smoke sensors in apartments - 25%;
- installation of doors in technical rooms - 85%;
- installation of low-voltage networks in the lobby - 55%.
Building No. 5, section 2:
- construction of walls and partitions on the 1st floor - 100%.
Building No. 5, section 3:
- construction of walls and partitions on the 10th, 11th, 12th floors - 40%.
Building No. 6, section 1:
- facade construction - 15%.
Building No. 6, section 2:
- facade construction - 80%.