Sharing fresh news from the construction site for June:

Building #3, parking:

  • work continues on laying polymer floor coating in the parking lot - 90%.

Building #3, landscaping:

  • work continues on landscaping the inner courtyard - 70%.

Building #4:

  • installation of smoke exhaust and parking ventilation systems - 80%;
  • landscaping of the territory - 15%;
  • installation of fire alarm systems, SPS - 85%;
  • installation of TP-5 (frame) - 90%;
  • ongoing electrical installation works in the parking lot - 70.

Building #4, section 1:

  • finishing of common areas from 3 to 13 floors (application of glass fiber on plasterboard ceilings, installation of ceramic baseboard and wall cladding in the elevator hall with ceramic tiles) - 90%;
  • embellishment of LMM facades - 70%;
  • installation of smoke exhaust valves and air support in technical rooms - 30%;
  • installation of boilers - 100%;
  • installation of metal structures under curved facade - 100%;
  • installation of aluminum structures under curved facade - 75%;
  • equipping PC cabinets in common areas - 100%;
  • installation of apartment metering nodes - 100%;
  • installation of smoke exhaust valves in apartments - 100%;
  • laying of low-current networks on the first floor - 60%;
  • brick laying on the first floor - 55%.

Building #4, section 2:

  • embellishment of LMM facades - 80%;
  • finishing of common areas from 3 to 13 floors - 75%;
  • installation of smoke exhaust and ventilation systems on the first floor - 90%;
  • installation of translucent protective structures (SPK) of the entrance group - 25%;
  • installation of heating boilers in apartments from 3 to 13 floors - 100%;
  • installation of doors in storage rooms and technical rooms - 95%;
  • installation of vents on ventilation shafts (roof) - 100%;
  • installation of metal structures under curved facade - 100%;
  • installation of aluminum structures under curved facade - 85%;
  • equipping PC cabinets in common areas - 100%;
  • installation of apartment metering nodes - 100%;
  • brick laying on the first floor - 60%.

Building #4, section 3:

  • finishing of common areas from 3 to 13 floors - 65%;
  • installation of heating boilers in apartments from 3 to 13 floors - 100%;
  • installation of metal structures under curved facade - 70%;
  • equipping PC cabinets in common areas - 100%;
  • installation of apartment metering nodes - 100%.

Building #5, section 1:

  • masonry of ventilation shafts (roof) - 90%.

Building #5, section 2:

  • installation of walls and partitions on the 1st floor - 95%.

Building #5, section 3:

  • installation of walls and partitions on the 2nd, 7th, 12th, 13th floors - 35%.

Building #6, section 1:

  • facade construction - 10%.

Building #6, section 2:

  • installation of floor soundproofing before laying cement-sand screed on 7-10 floors - 100%;
  • facade construction - 65%;
  • installation of HVAC systems on floors 1-14 and ventilation and air conditioning on floors 7-14 - 100%;
  • electrical installation works on floors 5-7 - 70%.