Construction progress for June 2025
01.07.2025
Go back
Sharing fresh news from the construction site for June:
Building #3, parking:
- work continues on laying polymer floor coating in the parking lot - 90%.
Building #3, landscaping:
- work continues on landscaping the inner courtyard - 70%.
Building #4:
- installation of smoke exhaust and parking ventilation systems - 80%;
- landscaping of the territory - 15%;
- installation of fire alarm systems, SPS - 85%;
- installation of TP-5 (frame) - 90%;
- ongoing electrical installation works in the parking lot - 70.
Building #4, section 1:
- finishing of common areas from 3 to 13 floors (application of glass fiber on plasterboard ceilings, installation of ceramic baseboard and wall cladding in the elevator hall with ceramic tiles) - 90%;
- embellishment of LMM facades - 70%;
- installation of smoke exhaust valves and air support in technical rooms - 30%;
- installation of boilers - 100%;
- installation of metal structures under curved facade - 100%;
- installation of aluminum structures under curved facade - 75%;
- equipping PC cabinets in common areas - 100%;
- installation of apartment metering nodes - 100%;
- installation of smoke exhaust valves in apartments - 100%;
- laying of low-current networks on the first floor - 60%;
- brick laying on the first floor - 55%.
Building #4, section 2:
- embellishment of LMM facades - 80%;
- finishing of common areas from 3 to 13 floors - 75%;
- installation of smoke exhaust and ventilation systems on the first floor - 90%;
- installation of translucent protective structures (SPK) of the entrance group - 25%;
- installation of heating boilers in apartments from 3 to 13 floors - 100%;
- installation of doors in storage rooms and technical rooms - 95%;
- installation of vents on ventilation shafts (roof) - 100%;
- installation of metal structures under curved facade - 100%;
- installation of aluminum structures under curved facade - 85%;
- equipping PC cabinets in common areas - 100%;
- installation of apartment metering nodes - 100%;
- brick laying on the first floor - 60%.
Building #4, section 3:
- finishing of common areas from 3 to 13 floors - 65%;
- installation of heating boilers in apartments from 3 to 13 floors - 100%;
- installation of metal structures under curved facade - 70%;
- equipping PC cabinets in common areas - 100%;
- installation of apartment metering nodes - 100%.
Building #5, section 1:
- masonry of ventilation shafts (roof) - 90%.
Building #5, section 2:
- installation of walls and partitions on the 1st floor - 95%.
Building #5, section 3:
- installation of walls and partitions on the 2nd, 7th, 12th, 13th floors - 35%.
Building #6, section 1:
- facade construction - 10%.
Building #6, section 2:
- installation of floor soundproofing before laying cement-sand screed on 7-10 floors - 100%;
- facade construction - 65%;
- installation of HVAC systems on floors 1-14 and ventilation and air conditioning on floors 7-14 - 100%;
- electrical installation works on floors 5-7 - 70%.