Construction progress for May 2025
02.06.2025
Go back
Sharing fresh news from the construction site for May:
Building No. 3, parking:
- installation of polymer floor coating for the parking lot.
Building No. 3, landscaping:
- ongoing landscaping of the inner courtyard;
Building No. 4:
- installation of smoke extraction and ventilation systems for the parking lot;
- installation of external power supply networks;
- arrangement of technical premises (floor screed, plastering);
- roofing of the external and inner courtyard parking lot.
Building No. 4, section 1:
- arrangement of technical premises from floors 3 to 13 (installation of glass fibre on plasterboard ceilings in technical premises, installation of ceramic skirting boards and tiling of walls in the lift lobby);
- embellishment of LMM facades;
- installation of smoke extraction and ventilation systems;
- installation of heating systems in apartments;
- installation of metal structures for the curved facade;
- installation of grids on ventilation shafts (roof).
- Building No. 4, section 2:
- embellishment of LMM facades;
painting of plasterboard ceilings in technical premises;
- installation of smoke extraction and ventilation systems on the first floor;
- installation of transparent protective structures (SPOK);
- installation of doors in storage rooms;
- continuation of hatch installation in technical premises from floors 3 to 13;
- installation of heating systems in apartments from floors 3 to 13;
- installation of boilers in apartments;
- installation of grids on ventilation shafts (roof).
- Building No. 4, section 3:
- arrangement of technical premises from floors 3 to 13 (installation of glass fibre on plasterboard ceilings, installation of ceramic skirting boards and tiling of walls in the lift lobby);
installation of hatches from floors 3 to 13;
- installation of heating systems in apartments from floors 3 to 13.
- Building No. 5, section 1:
- construction of walls and partitions on floors 1, 2, 14, and roof.
Building No. 5, section 2:
- construction of walls and partitions on the 1st floor.
Building No. 5, section 3:
- construction of walls and partitions on floors 3, 7;
roofing of the parking lot.
- Building No. 5, Parking 1.6 (parking adjacent to section 3):
- roofing of the parking lot.
Building No. 6, section 1:
- facade construction.
Building No. 6, section 2:
- installation of floor soundproofing before laying cement screed on floors 3-7;
facade construction;
- installation of systems for floors 1-14 and ventilation on floors 3-7;
- electrical works on floors 3-7.