Construction progress for May 2025

02.06.2025

Go back

Sharing fresh news from the construction site for May:

Building No. 3, parking:

  • installation of polymer floor coating for the parking lot.

Building No. 3, landscaping:

  • ongoing landscaping of the inner courtyard;

Building No. 4:

  • installation of smoke extraction and ventilation systems for the parking lot;
  • installation of external power supply networks;
  • arrangement of technical premises (floor screed, plastering);
  • roofing of the external and inner courtyard parking lot.

Building No. 4, section 1:

  • arrangement of technical premises from floors 3 to 13 (installation of glass fibre on plasterboard ceilings in technical premises, installation of ceramic skirting boards and tiling of walls in the lift lobby);
  • embellishment of LMM facades;
  • installation of smoke extraction and ventilation systems;
  • installation of heating systems in apartments;
  • installation of metal structures for the curved facade;
  • installation of grids on ventilation shafts (roof).
  • Building No. 4, section 2:
  • embellishment of LMM facades;

painting of plasterboard ceilings in technical premises;

  • installation of smoke extraction and ventilation systems on the first floor;
  • installation of transparent protective structures (SPOK);
  • installation of doors in storage rooms;
  • continuation of hatch installation in technical premises from floors 3 to 13;
  • installation of heating systems in apartments from floors 3 to 13;
  • installation of boilers in apartments;
  • installation of grids on ventilation shafts (roof).
  • Building No. 4, section 3:
  • arrangement of technical premises from floors 3 to 13 (installation of glass fibre on plasterboard ceilings, installation of ceramic skirting boards and tiling of walls in the lift lobby);

installation of hatches from floors 3 to 13;

  • installation of heating systems in apartments from floors 3 to 13.
  • Building No. 5, section 1:
  • construction of walls and partitions on floors 1, 2, 14, and roof.

Building No. 5, section 2:

  • construction of walls and partitions on the 1st floor.

Building No. 5, section 3:

  • construction of walls and partitions on floors 3, 7;

roofing of the parking lot.

  • Building No. 5, Parking 1.6 (parking adjacent to section 3):
  • roofing of the parking lot.

Building No. 6, section 1:

  • facade construction.

Building No. 6, section 2:

  • installation of floor soundproofing before laying cement screed on floors 3-7;

facade construction;

  • installation of systems for floors 1-14 and ventilation on floors 3-7;
  • electrical works on floors 3-7.