Construction progress for March 2025
01.04.2025
Sharing fresh news from the construction site for March:
Building #3, parking:
- installation of polymer floor coating in the parking lot.
Building #3, improvement:
- continuing the improvement of the inner courtyard;
- improvement of the area near the sales office.
Building #4:
- installation of smoke extraction and ventilation systems in the parking lot;
- improvement of the area;
- installation of fire alarm systems, fire extinguishing systems;
- installation of water supply systems;
- installation of transformer substation-5;
- electrical works in the parking lot;
- installation of parking lot roof.
Building #4, section 1:
- installation of radiators in apartments;
- finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);
- decoration of facade spaces;
- construction of 1st and 2nd floor walls;
- installation of smoke extraction and ventilation systems;
- installation of PVC structures on the podium part;
- ongoing works on decoration of technical rooms (painting walls, insulating ceiling);
- installation of fire extinguishing systems in technical rooms;
- continuing installation of doors in storage rooms;
- continuing installation of hatches on 3rd to 13th floor.
Building #4, section 2:
- continuing installation of doors in storage rooms;
- continuing installation of hatches on 3rd to 13th floor.
decoration of facade spaces;
finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);
construction of 1st and 2nd floor walls;
installation of translucent protective structures (TSK);
ongoing works on decoration of technical rooms (painting walls, insulating ceiling);
Building #4, section 3:
finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);
installation of smoke extraction and ventilation systems;
installation of translucent protective structures (TSK);
ongoing works on decoration of technical rooms (painting walls, insulating ceiling);
electrical works on 9th to 13th floors;
installation of entrance doors from 3rd to 13th floor.
Building #5, section 1:
- construction of walls and partitions on the 2nd, 11th, 12th, 13th floors;
- installation of vertical elements of the monolithic parapet.
Building #5, section 2:
- construction of walls and partitions on the 2nd, 11th, 13th, 14th floors.
Building #5, section 3:
- construction of walls and partitions on the 1st, 6th, 7th floors;
- installation of parking lot roof.
Building #5, parking 1.6 (parking adjacent to section 3):
- installation of vertical and horizontal elements of the monolithic frame on the 1st floor.
Building #6, section 1:
- installation of metal-plastic window structures on the 12th, 13th, 14th floors;
- facade construction.
Building #6, section 2:
- facade construction.