Construction progress for March 2025

01.04.2025

Go back

Sharing fresh news from the construction site for March:

Building #3, parking:

  • installation of polymer floor coating in the parking lot.

Building #3, improvement:

  • continuing the improvement of the inner courtyard;
  • improvement of the area near the sales office.

Building #4:

  • installation of smoke extraction and ventilation systems in the parking lot;
  • improvement of the area;
  • installation of fire alarm systems, fire extinguishing systems;
  • installation of water supply systems;
  • installation of transformer substation-5;
  • electrical works in the parking lot;
  • installation of parking lot roof.

Building #4, section 1:

  • installation of radiators in apartments;
  • finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);
  • decoration of facade spaces;
  • construction of 1st and 2nd floor walls;
  • installation of smoke extraction and ventilation systems;
  • installation of PVC structures on the podium part;
  • ongoing works on decoration of technical rooms (painting walls, insulating ceiling);
  • installation of fire extinguishing systems in technical rooms;
  • continuing installation of doors in storage rooms;
  • continuing installation of hatches on 3rd to 13th floor.

Building #4, section 2:

    decoration of facade spaces;

    finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);

    construction of 1st and 2nd floor walls;

    installation of translucent protective structures (TSK);

    ongoing works on decoration of technical rooms (painting walls, insulating ceiling);

  • continuing installation of doors in storage rooms;
  • continuing installation of hatches on 3rd to 13th floor.

Building #4, section 3:

    finishing of the common area from 3rd to 13th floor (installation of gypsum ceiling);

    installation of smoke extraction and ventilation systems;

    installation of translucent protective structures (TSK);

    ongoing works on decoration of technical rooms (painting walls, insulating ceiling);

    electrical works on 9th to 13th floors;

    installation of entrance doors from 3rd to 13th floor.

Building #5, section 1:

  • construction of walls and partitions on the 2nd, 11th, 12th, 13th floors;
  • installation of vertical elements of the monolithic parapet.

Building #5, section 2:

  • construction of walls and partitions on the 2nd, 11th, 13th, 14th floors.

Building #5, section 3:

  • construction of walls and partitions on the 1st, 6th, 7th floors;
  • installation of parking lot roof.

Building #5, parking 1.6 (parking adjacent to section 3):

  • installation of vertical and horizontal elements of the monolithic frame on the 1st floor.

Building #6, section 1:

  • installation of metal-plastic window structures on the 12th, 13th, 14th floors;
  • facade construction.

Building #6, section 2:

  • facade construction.