Construction progress for April 2026
01.05.2026
Go back
We are sharing the latest construction updates for April:
Inner courtyard:
preparatory works for the installation of a children’s playground have started
Building No. 4, Section 1:
- installation of suspended ceilings in common areas (cube-slat system) from the 8th to the 13th floors (overall completion — 100%)
- joint waterproofing (SPOK) — 100%
- installation of the lobby suspended ceiling frame — 100%
Building No. 4, Section 2:
- application of decorative plaster in common areas on the 5th floor — 80% (overall completion — 15%)
- installation of fire protection systems in commercial premises
Building No. 4, Section 3:
- installation of suspended ceilings in common areas (cube-slat system) from the 3rd to the 8th floors (overall completion — 60%)
- application of decorative plaster in common areas on the 8th and 9th floors — 60% (overall completion from 3rd to 9th floors — 80%)
- painting works of staircases have started
- tiling works in staircases — 70%
Building No. 4, Parking:
- masonry works for entrance/exit gate openings — 70%
- waterproofing of basement common area floors — 90%
Building No. 5, Section 1:
- roof insulation works — 100%
- roof waterproofing works in progress
Building No. 5, Section 2:
- roof insulation and waterproofing works
Building No. 5, Section 3:
- preparatory works for window installation have started
- roofing works
Parking No. 1.5 (adjacent to Building No. 5, Sections 1–2):
- roofing works
Building No. 6, Section 1:
- façade works in progress