LUCKY LAND
Construction progress for April 2026

01.05.2026

Go back

We are sharing the latest construction updates for April:

Inner courtyard:

preparatory works for the installation of a children’s playground have started

Building No. 4, Section 1:

  • installation of suspended ceilings in common areas (cube-slat system) from the 8th to the 13th floors (overall completion — 100%)
  • joint waterproofing (SPOK) — 100%
  • installation of the lobby suspended ceiling frame — 100%

Building No. 4, Section 2:

  • application of decorative plaster in common areas on the 5th floor — 80% (overall completion — 15%)
  • installation of fire protection systems in commercial premises

Building No. 4, Section 3:

  • installation of suspended ceilings in common areas (cube-slat system) from the 3rd to the 8th floors (overall completion — 60%)
  • application of decorative plaster in common areas on the 8th and 9th floors — 60% (overall completion from 3rd to 9th floors — 80%)
  • painting works of staircases have started
  • tiling works in staircases — 70%

Building No. 4, Parking:

  • masonry works for entrance/exit gate openings — 70%
  • waterproofing of basement common area floors — 90%

Building No. 5, Section 1:

  • roof insulation works — 100%
  • roof waterproofing works in progress

Building No. 5, Section 2:

  • roof insulation and waterproofing works

Building No. 5, Section 3:

  • preparatory works for window installation have started
  • roofing works

Parking No. 1.5 (adjacent to Building No. 5, Sections 1–2):

  • roofing works

Building No. 6, Section 1:

  • façade works in progress