Construction Progress for August 2026

03.09.2026

Go back
  • Sharing the latest construction site updates for August:
  • Building No. 4, Section 1:

    • Installation of porcelain stoneware flooring has been completed;
    • Puttying of walls and ceilings on the 1st and 2nd floors has begun;
    • Installation of glass façades is ongoing;
    • Installation of terrace railings for the apartments has begun.

    Building No. 4, Section 2:

    • Façade works are ongoing, and installation of Aquapanel boards in the unheated passageways has begun;
    • Finishing works in the common areas are 60% complete;
    • Installation of flooring on the staircases has begun;
    • Flooring works in the basement areas are 80% complete.

    Building No. 4, Section 3:

    • Installation of lighting fixtures has been completed;
    • Installation of porcelain stoneware flooring in the lobby has been completed;
    • Installation of porcelain stoneware flooring in the basement areas has been completed;
    • Installation of tiles in the elevator halls has begun;
    • Installation of plasterboard ceilings in the lobby has begun.

    Building No. 6, Section 1:

    • Façade works are ongoing, with insulation 75% complete;
    • Application of textured coating — 50%;
    • Clinker-effect painting — 30%;
    • Brickwork — 95%.

    Building No. 6, Section 2:

    • Installation of doors in the unheated passageways — 50%;
    • Floor screed has been completed on 8 floors;
    • Installation of parapet caps on the roof has begun;
    • Brickwork on the first floor — 85%.

    Building No. 5, Section 3:

    • Windows have been installed on the façade facing Palladina Avenue from the 3rd to the 12th floor.

    Children’s playground:

    • Retaining walls have been concreted, and foundation pits for the structures have been excavated.