Construction Progress for August 2026
03.09.2026
Go back
Building No. 4, Section 1:
- Installation of porcelain stoneware flooring has been completed;
- Puttying of walls and ceilings on the 1st and 2nd floors has begun;
- Installation of glass façades is ongoing;
- Installation of terrace railings for the apartments has begun.
Building No. 4, Section 2:
- Façade works are ongoing, and installation of Aquapanel boards in the unheated passageways has begun;
- Finishing works in the common areas are 60% complete;
- Installation of flooring on the staircases has begun;
- Flooring works in the basement areas are 80% complete.
Building No. 4, Section 3:
- Installation of lighting fixtures has been completed;
- Installation of porcelain stoneware flooring in the lobby has been completed;
- Installation of porcelain stoneware flooring in the basement areas has been completed;
- Installation of tiles in the elevator halls has begun;
- Installation of plasterboard ceilings in the lobby has begun.
Building No. 6, Section 1:
- Façade works are ongoing, with insulation 75% complete;
- Application of textured coating — 50%;
- Clinker-effect painting — 30%;
- Brickwork — 95%.
Building No. 6, Section 2:
- Installation of doors in the unheated passageways — 50%;
- Floor screed has been completed on 8 floors;
- Installation of parapet caps on the roof has begun;
- Brickwork on the first floor — 85%.
Building No. 5, Section 3:
- Windows have been installed on the façade facing Palladina Avenue from the 3rd to the 12th floor.
Children’s playground:
- Retaining walls have been concreted, and foundation pits for the structures have been excavated.