Construction Progress for July 2026
03.08.2026
Sharing the latest construction site updates for July:
Building 4, Section 1:
Installation of porcelain stoneware flooring in the common areas of the basement: Level -1 completed, Level -2 – 50% complete;
Plumbing connections in the lobby completed;
Glass façade installation is ongoing – 80% complete;
LMM façade installation is ongoing – 80% complete.
Building 4, Section 2:
LMM façade installation is ongoing – 80% complete.
Building 4, Section 3:
Decorative plaster application completed;
Installation of apartment electrical distribution panels completed;
Installation of linear light fixtures – 90% complete;
Plumbing rough-ins for sanitary fixtures in the lobby completed;
Installation of porcelain stoneware flooring in the lobby – 60% complete;
Installation of porcelain stoneware flooring in the basement areas on Level -1 is ongoing.
Building 5, Section 3:
Window installation is ongoing on the 3rd, 4th, and 5th floors.
Inner Courtyard:
The concrete slab has been completed; retaining walls are currently being concreted.
Building 6, Section 1:
Façade works are ongoing; insulation is 75% complete;
Textured finish application – 30% complete;
Clinker-effect painting – 15% complete;
Construction of ceramic block walls on the first floor has begun;
Thermal insulation and waterproofing of the slab above the parking garage – 15% complete.
Building 6, Section 2:
Thermal insulation and waterproofing of the slab above the parking garage – 15% complete;
Installation of heating pipes beneath the screed completed;
Floor screed completed up to the 4th floor.