Construction Progress for July 2026

03.08.2026

Go back

Sharing the latest construction site updates for July:

Building 4, Section 1:

  • Installation of porcelain stoneware flooring in the common areas of the basement: Level -1 completed, Level -2 – 50% complete;

  • Plumbing connections in the lobby completed;

  • Glass façade installation is ongoing – 80% complete;

  • LMM façade installation is ongoing – 80% complete.

Building 4, Section 2:

  • LMM façade installation is ongoing – 80% complete.

Building 4, Section 3:

  • Decorative plaster application completed;

  • Installation of apartment electrical distribution panels completed;

  • Installation of linear light fixtures – 90% complete;

  • Plumbing rough-ins for sanitary fixtures in the lobby completed;

  • Installation of porcelain stoneware flooring in the lobby – 60% complete;

  • Installation of porcelain stoneware flooring in the basement areas on Level -1 is ongoing.

Building 5, Section 3:

  • Window installation is ongoing on the 3rd, 4th, and 5th floors.

Inner Courtyard:

  • The concrete slab has been completed; retaining walls are currently being concreted.

Building 6, Section 1:

  • Façade works are ongoing; insulation is 75% complete;

  • Textured finish application – 30% complete;

  • Clinker-effect painting – 15% complete;

  • Construction of ceramic block walls on the first floor has begun;

  • Thermal insulation and waterproofing of the slab above the parking garage – 15% complete.

Building 6, Section 2:

  • Thermal insulation and waterproofing of the slab above the parking garage – 15% complete;

  • Installation of heating pipes beneath the screed completed;

  • Floor screed completed up to the 4th floor.