LUCKY LAND
Construction progress for March 2026

02.04.2026

Go back

Sharing fresh news from the construction site for March:

Building No. 4, section 1:

  • installation of suspended ceiling in the common area with cube-rail from the 3rd to the 8th floor - 95% (total for the section - 60%)
  • installation of insulation at the junctions of abutments (SPOK) - 100%
  • installation of suspended ceiling frame in the lobby - 100%

Building No. 4, section 2:

  • concreting of technological openings for the passage of engineering communications through apartments - 100%
  • application of decorative plaster in the common area on the 4th floor - 95% (total for the section - 10%)

Building No. 4, section 3:

  • concreting of technological openings for the passage of engineering communications through apartments - 100%
  • application of decorative plaster in the common area on the 7th floor - 100% (total for the section from the 3rd to the 7th floor - 100%)

Building No. 4, parking:

  • started masonry of openings for the entrance-exit gate

Building No. 5, section 1:

  • started insulation work for the roof

Substation 5 (Transformer substation):

  • completed insulation and construction of roof pitch