Construction progress for March 2026
02.04.2026
Go back
Sharing fresh news from the construction site for March:
Building No. 4, section 1:
- installation of suspended ceiling in the common area with cube-rail from the 3rd to the 8th floor - 95% (total for the section - 60%)
- installation of insulation at the junctions of abutments (SPOK) - 100%
- installation of suspended ceiling frame in the lobby - 100%
Building No. 4, section 2:
- concreting of technological openings for the passage of engineering communications through apartments - 100%
- application of decorative plaster in the common area on the 4th floor - 95% (total for the section - 10%)
Building No. 4, section 3:
- concreting of technological openings for the passage of engineering communications through apartments - 100%
- application of decorative plaster in the common area on the 7th floor - 100% (total for the section from the 3rd to the 7th floor - 100%)
Building No. 4, parking:
- started masonry of openings for the entrance-exit gate
Building No. 5, section 1:
- started insulation work for the roof
Substation 5 (Transformer substation):
- completed insulation and construction of roof pitch