Construction progress for May 2026
01.06.2026
Go back
Building No. 4, Section 1:
- Plastering of the common corridor in the commercial premises – 100% completed.
- Screed installation works in the basement common areas have commenced – 15% completed.
Building No. 4, Section 2:
- Rough electrical installation works in the lobby – 100% completed.
- Plastering of the common corridor in the commercial premises – 100% completed.
- Lobby plastering works have commenced – 15% completed.
- Decorative plaster application in common areas on floors 5–7 – 100% completed (overall completion for the section: 40%).
- Installation of fire protection and smoke detection systems in commercial premises is ongoing.
Building No. 4, Section 3:
- Decorative plaster application in common areas on floors 8–9 – 95% completed (overall completion from floors 3–9: 95%).
- Stairwell painting – 90% completed.
- Stairwell tiling works are ongoing – 95% completed.
Building No. 4, Parking:
- Waterproofing works for the basement common area floor – 100% completed.
Building No. 5, Section 1:
- Roof waterproofing works – 100% completed.
Building No. 5, Section 2:
- Roof waterproofing works – 100% completed.
Building No. 5, Section 3:
- Roof insulation works have been completed.
- Roof waterproofing works are ongoing.
TP-5 (Transformer Substation):
- Installation of chamber KK13 has been completed.
- External power network installation works have commenced.
Building No. 6, Section 1:
- Facade installation works are ongoing.
Inner Courtyard:
- Preparatory works for the children's playground have been completed.
- Crushed stone base and preparatory concrete layer – 100% completed.