Construction progress for May 2026

01.06.2026

Go back
  • We are sharing the latest construction site updates for May:
  • Building No. 4, Section 1:

    • Plastering of the common corridor in the commercial premises – 100% completed.
    • Screed installation works in the basement common areas have commenced – 15% completed.

    Building No. 4, Section 2:

    • Rough electrical installation works in the lobby – 100% completed.
    • Plastering of the common corridor in the commercial premises – 100% completed.
    • Lobby plastering works have commenced – 15% completed.
    • Decorative plaster application in common areas on floors 5–7 – 100% completed (overall completion for the section: 40%).
    • Installation of fire protection and smoke detection systems in commercial premises is ongoing.

    Building No. 4, Section 3:

    • Decorative plaster application in common areas on floors 8–9 – 95% completed (overall completion from floors 3–9: 95%).
    • Stairwell painting – 90% completed.
    • Stairwell tiling works are ongoing – 95% completed.

    Building No. 4, Parking:

    • Waterproofing works for the basement common area floor – 100% completed.

    Building No. 5, Section 1:

    • Roof waterproofing works – 100% completed.

    Building No. 5, Section 2:

    • Roof waterproofing works – 100% completed.

    Building No. 5, Section 3:

    • Roof insulation works have been completed.
    • Roof waterproofing works are ongoing.

    TP-5 (Transformer Substation):

    • Installation of chamber KK13 has been completed.
    • External power network installation works have commenced.

    Building No. 6, Section 1:

    • Facade installation works are ongoing.

    Inner Courtyard:

    • Preparatory works for the children's playground have been completed.
    • Crushed stone base and preparatory concrete layer – 100% completed.