Construction progress in February 2026

04.03.2026

Go back

Sharing fresh news from the construction site for February:

Building №4, section 1:

  • insulation installation on the stair landing - 95%
  • concreting of technological holes for the passage of engineering communications through apartments - 100%

Building №4, section 2:

  • insulation installation on the junctions of adjoinings (SPAC) - 100%
  • concreting of technological holes for the passage of engineering communications through apartments - 75%

Building №4, section 3:

  • insulation installation on the junctions of adjoinings (SPAC) - 100%
  • decorative plastering in common areas on the 7th floor - 80%

Building №5, section 2:

  • masonry of walls and partitions in the basement premises - 85%

Building №5, section 3:

  • masonry of walls and partitions in the basement premises - 100%