Construction progress in February 2026
04.03.2026
Go back
Sharing fresh news from the construction site for February:
Building №4, section 1:
- insulation installation on the stair landing - 95%
- concreting of technological holes for the passage of engineering communications through apartments - 100%
Building №4, section 2:
- insulation installation on the junctions of adjoinings (SPAC) - 100%
- concreting of technological holes for the passage of engineering communications through apartments - 75%
Building №4, section 3:
- insulation installation on the junctions of adjoinings (SPAC) - 100%
- decorative plastering in common areas on the 7th floor - 80%
Building №5, section 2:
- masonry of walls and partitions in the basement premises - 85%
Building №5, section 3:
- masonry of walls and partitions in the basement premises - 100%