Construction progress in January 2026

30.01.2026

Go back

Sharing fresh news from the construction site for January:

House No.3, landscaping:

  • installation of automatic irrigation system - 90%

House No.4, section 1:

  • started installation of insulation on the stairwell - 2%
  • painting walls and ceiling on stairwells - 95%

House No.4, section 2:

  • installation of insulation on junction points (SPAC) - 80%

House No.4, section 3:

  • installation of insulation on junction points (SPAC) - 90%
  • decorative stucco on the stairs

House No.5, section 1:

  • masonry of walls and partitions in the basement - 100%

House No.5, section 2:

  • masonry of walls and partitions in the basement - 60%

House No.5, section 3:

  • masonry of walls and partitions in the basement - 98%

House No.6, section 2:

  • installation of K2 system risers - 100%