Construction progress in January 2026
30.01.2026
Go back
Sharing fresh news from the construction site for January:
House No.3, landscaping:
- installation of automatic irrigation system - 90%
House No.4, section 1:
- started installation of insulation on the stairwell - 2%
- painting walls and ceiling on stairwells - 95%
House No.4, section 2:
- installation of insulation on junction points (SPAC) - 80%
House No.4, section 3:
- installation of insulation on junction points (SPAC) - 90%
- decorative stucco on the stairs
House No.5, section 1:
- masonry of walls and partitions in the basement - 100%
House No.5, section 2:
- masonry of walls and partitions in the basement - 60%
House No.5, section 3:
- masonry of walls and partitions in the basement - 98%
House No.6, section 2:
- installation of K2 system risers - 100%