Construction progress for April 2025
02.05.2025
Go back
Sharing the latest news from the construction site for April:
Building No.3, section 1:
- installation of heating radiators completed from the 3rd to the 30th floor, installation continues on the 31st floor;
- ceramic tile flooring works completed in the MZK and elevator lobby from the 3rd to the 20th floor, works continue from the 21st to the 25th floor;
- disconnection of VK, OE risers - 80%;
- preparation and application of decorative plaster from the 5th to the 15th floor;
- ceiling display on the 5th floor completed.
Building No.3, section 2:
- 95% of balcony fences completed;
- facade repairs of LMM - 68% completed;
- preparatory works for finishing the MZK in progress;
- installation of air conditioner baskets completed.
Building No.3, section 3:
- installation of air conditioner baskets in progress - 80%;
- installation of the last elevator in progress;
- electrical panel assembly in the parking lot;
- preparatory works completed for applying decorative coating on walls from the 6th to the 34th floor;
- ceramic tile installation continues on the walls in the MZK and elevator lobby from the 28th to the 34th floor.
Parking lot No.3:
- works on waterproofing the parking slab in progress: adhesion, keramzit concrete casting, membrane installation, drainage membrane, geotextile, protective plate reinforcement and concreting - 20%.
Building No.4, section 1:
- continuation of works on the construction of vertical monolithic structures of the 34th floor and slab;
- brick wall laying completed from the 1st to the 27th floor - 90%, works continue from the 28th to the 30th floor - 80%;
- staircase installation - 70%;
- ventilation block installation completed up to the 27th floor, works continue on the 28th floor - 50%.
Building No.4, section 2:
- monolithic frame completed from the 1st to the 9th floor. Work on the 10th floor slab;
staircase construction from -4.200 to the 4th floor completed, works continue from the 4th to the 5th floor.
- Building No.4, section 3:
- brick wall laying from the 2nd to the 8th floor - 90%;
staircase installation - 47%.
- Building No.4, section 5:
staircase installation - 28%.
- Parking lot No.4:
- works in progress: railing installation, gravel filling, subbase;