Sharing the latest news from the construction site for March:

Building No.3, section 1:

  • installation of heating radiators completed from the 3rd to the 28th floor, installation continues on the 29th floor;
  • 87% of boilers installed;
  • installation of elevators completed;
  • work done on laying ceramic tiles on the floor of the common areas and elevator lobby from the 3rd to the 18th floor;
  • work in progress on installation of air ducts and fire protection;
  • disconnection of vertical risers, completion – 70%.

Building No.3, section 2:

  • 92% of balcony fences installed;
  • facade repair completed, progress – 67%;
  • preparatory work for finishing the common areas in progress.

Building No.3, section 3:

  • installation of air conditioner brackets in progress – 40%;
  • installation of 2 elevators started – 50%;
  • electrical works: installation of switchgear completed, assembly of electrical panels in progress in the parking area;
  • preparatory work done for applying decorative wall finish from the 18th to the 34th floor;
  • work in progress on laying ceramic tiles on the walls of the common areas and elevator lobby from the 28th to the 34th floor.

Parking Garage No.3:hydroisolation work, joint arrangement, and lightweight concrete installation in progress;

  • landscaping concept approved, development of working documentation ongoing.
  • Building No.4, section 1:

completed monolithic frame from the 1st to the 33rd floor. Work on the vertical structure and the 34th-floor slabs ongoing;

  • brickwork on walls from the 1st to the 26th floor – 90%, work continues from the 27th to the 29th floor – 70%;
  • installation of stair flights – 65%;
  • ventilation block installation completed up to the 24th floor. 25th floor – 90%, work continues on the 26th floor.
  • Building No.4, section 2:

completed monolithic frame from the 1st to the 6th floor. Work on the 7th-floor slab ongoing;

  • stairwell construction completed from -4.200 to the 2nd floor. Work ongoing from the 2nd to the 3rd floor.
  • Building No.4, section 3:

brickwork on walls from the 2nd to the 8th floor – 90%;

  • installation of stair flights – 45%;
  • ventilation block installation completed up to the 15th floor.
  • Building No.4, section 5:

brickwork completed up to the 5th floor;

  • installation of stair flights – 25%.
  • Parking Garage No.4:

ramp installation completed – 100%;

  • excavation work and soil removal ongoing;
  • hydroisolation work on walls and ramps in progress.
  • External networks:

90% completion of relocation of 10kV power lines;

  • tender procedure ongoing to select a design organization for the gas supply project for building No.4.