Construction progress for March 2025
02.04.2025
Go back
Sharing the latest news from the construction site for March:
Building No.3, section 1:
- installation of heating radiators completed from the 3rd to the 28th floor, installation continues on the 29th floor;
- 87% of boilers installed;
- installation of elevators completed;
- work done on laying ceramic tiles on the floor of the common areas and elevator lobby from the 3rd to the 18th floor;
- work in progress on installation of air ducts and fire protection;
- disconnection of vertical risers, completion – 70%.
Building No.3, section 2:
- 92% of balcony fences installed;
- facade repair completed, progress – 67%;
- preparatory work for finishing the common areas in progress.
Building No.3, section 3:
- installation of air conditioner brackets in progress – 40%;
- installation of 2 elevators started – 50%;
- electrical works: installation of switchgear completed, assembly of electrical panels in progress in the parking area;
- preparatory work done for applying decorative wall finish from the 18th to the 34th floor;
- work in progress on laying ceramic tiles on the walls of the common areas and elevator lobby from the 28th to the 34th floor.
Parking Garage No.3:hydroisolation work, joint arrangement, and lightweight concrete installation in progress;
- landscaping concept approved, development of working documentation ongoing.
- Building No.4, section 1:
completed monolithic frame from the 1st to the 33rd floor. Work on the vertical structure and the 34th-floor slabs ongoing;
- brickwork on walls from the 1st to the 26th floor – 90%, work continues from the 27th to the 29th floor – 70%;
- installation of stair flights – 65%;
- ventilation block installation completed up to the 24th floor. 25th floor – 90%, work continues on the 26th floor.
- Building No.4, section 2:
completed monolithic frame from the 1st to the 6th floor. Work on the 7th-floor slab ongoing;
- stairwell construction completed from -4.200 to the 2nd floor. Work ongoing from the 2nd to the 3rd floor.
- Building No.4, section 3:
brickwork on walls from the 2nd to the 8th floor – 90%;
- installation of stair flights – 45%;
- ventilation block installation completed up to the 15th floor.
- Building No.4, section 5:
brickwork completed up to the 5th floor;
- installation of stair flights – 25%.
- Parking Garage No.4:
ramp installation completed – 100%;
- excavation work and soil removal ongoing;
- hydroisolation work on walls and ramps in progress.
- External networks:
90% completion of relocation of 10kV power lines;
- tender procedure ongoing to select a design organization for the gas supply project for building No.4.
- Construction progress for March 2025