Sharing the latest news from the construction site for November:

Building #3, section 1:

  • installation of fire alarm system in progress;
  • decorating the lobby and installing suspended ceilings with plasterboard started;
  • ceramic tile installation on balconies — 100%;
  • lobby air conditioning system installation — 95%.

Building #3, section 2:

  • decorating staircases — 60%;
  • installation of suspended ceilings with cubic rail — 10%.

Building #3, section 3:

  • lobby decoration and wall plastering in progress — 90%.

Parking garage #3:

  • insulating and cladding emergency exit facade — 100%;
  • continuing floor installation works in the parking garage (grinding diffusion joints, waterproofing and laying fiber concrete floors) — 15%.

Landscaping of Zone 1 in Parking Garage #3:

  • earthworks in progress;
  • construction of RP started.

Building #4, section 1:

  • brick walls construction from 1st to 32nd floor — 100%, work from 33rd to 34th floor — 60%.

Building #4, section 2:

  • brick walls construction for technical floor — 95%.

Building #4, section 3:

  • brick walls construction for 11th floor — 100%.

Building #4, section 5:

  • installation of ventilation units on the 14th floor — 100%.

Parking garage #4:

  • waterproofing of piles, pile caps, and slab waterproofing in progress — 70%;
  • vertical construction works in progress — 85%, slab construction — 65%.