Construction progress for November 2025
05.12.2025
Go back
Sharing the latest news from the construction site for November:
Building #3, section 1:
- installation of fire alarm system in progress;
- decorating the lobby and installing suspended ceilings with plasterboard started;
- ceramic tile installation on balconies — 100%;
- lobby air conditioning system installation — 95%.
Building #3, section 2:
- decorating staircases — 60%;
- installation of suspended ceilings with cubic rail — 10%.
Building #3, section 3:
- lobby decoration and wall plastering in progress — 90%.
Parking garage #3:
- insulating and cladding emergency exit facade — 100%;
- continuing floor installation works in the parking garage (grinding diffusion joints, waterproofing and laying fiber concrete floors) — 15%.
Landscaping of Zone 1 in Parking Garage #3:
- earthworks in progress;
- construction of RP started.
Building #4, section 1:
- brick walls construction from 1st to 32nd floor — 100%, work from 33rd to 34th floor — 60%.
Building #4, section 2:
- brick walls construction for technical floor — 95%.
Building #4, section 3:
- brick walls construction for 11th floor — 100%.
Building #4, section 5:
- installation of ventilation units on the 14th floor — 100%.
Parking garage #4:
- waterproofing of piles, pile caps, and slab waterproofing in progress — 70%;
- vertical construction works in progress — 85%, slab construction — 65%.